112 Wildwood Completed

Montclair · PM: Herson

Phase Timeline · QB spend = financial record (transaction dates may not match work timing)

P1
P1
Done ✓ · 4d behind
P2
P2
Done ✓ · 44d behind
P3
P3
Done ✓ · 32d behind
PM Delay Notes Salt System for the Pool Salt System Electric Hook-Up

Activity Log

Week of Aug 18, 2025 P3
Mon Pool Inspection 10am
Tue Smoke Cert Inspection 10-12pm
Wed TBD Pending Buyers
Thu TBD Pending Buyers
Fri CLOSING DATE
QB recorded · $2.71M — seg 99: $1.80M, seg UNKNOWN: $778K · Township of Montclair, All-in Pools LLC — transaction dates may not match exact work timing
Week of Aug 11, 2025 P3
Mon Pool
Tue Pool
Wed Pool
Thu Pool
Fri Pool
QB recorded · $912 — seg 14: $644, seg 20: $194 · PSE&G, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Aug 4, 2025 P3
Mon Buyer's Inspections 10am / 12:30pm
Tue TBD Pending Buyer Decision
Wed TBD Pending Buyer Decision
Thu TBD Pending Buyer Decision
Fri TBD Pending Buyer Decision
QB recorded · $2K — seg 18: $1K, seg 20: $628 · Ashpa Management, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Jul 28, 2025 P3
Mon TBD Pending Buyer Decision
Tue TBD Pending Buyer Decision
Wed TBD Pending Buyer Decision
Thu TBD Pending Buyer Decision
Fri TBD Pending Buyer Decision
QB recorded · $15K — seg 13: $12K, seg 14: $2K · Township of Montclair, Hoffinger Yaacov — transaction dates may not match exact work timing
Week of Jul 21, 2025 P3
Mon TBD Pending Buyer Decision
Tue TBD Pending Buyer Decision
Wed TBD Pending Buyer Decision
Thu TBD Pending Buyer Decision
Fri TBD Pending Buyer Decision
QB recorded · $50 — seg 14: $50 · A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Jul 14, 2025 P3
Mon TBD Pending Buyer Decision
Tue TBD Pending Buyer Decision
Wed TBD Pending Buyer Decision
Thu TBD Pending Buyer Decision
Fri TBD Pending Buyer Decision
Week of Jul 7, 2025 P3
Mon TBD Pending Buyer Decision
Tue TBD Pending Buyer Decision
Wed TBD Pending Buyer Decision
Thu TBD Pending Buyer Decision
Fri Pool Salt System Arrives at Office
QB recorded · $26K — seg UNKNOWN: $14K, seg 63: $6K · Yover Tenezaca (Plumber), PSE&G — transaction dates may not match exact work timing
Week of Jun 30, 2025 P3
Mon Pool Salt System
Tue Pool Salt System
Wed Pool Salt System
Thu Pool Salt System
Fri 4th of July
QB recorded · $17K — seg 13: $12K, seg 62: $4K · Blue Ridge Lumber, Township of Montclair — transaction dates may not match exact work timing
Week of Jun 23, 2025 P3
Mon All Final Inspections 8-1pm
Tue Dave Nelson Photos 11am
Wed Pool Salt System
Thu Pool Salt System
Fri Pool Salt System
QB recorded · $2K — seg 20: $2K, seg 14: $525 · Buildesign Home Improvement, LLC, INYOO Pools — transaction dates may not match exact work timing
Week of Jun 16, 2025 P3
Mon Pool Salt System / Prep for Inspections
Tue Pool Salt System / Prep for Inspections
Wed Pool Salt System / Prep for Inspections
Thu Pool Salt System / Prep for Inspections
Fri Pool Salt System / Prep for Inspections
QB recorded · $28K — seg 14: $14K, seg 84: $7K · A-R General Contractor_Alberto Landscape & Snow Removal, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Jun 9, 2025 P3
Mon Exterior Photos 11:30am
Tue Final Touch Ups if Needed
Wed Final Touch Ups if Needed
Thu Final Touch Ups if Needed
Fri Final Touch Ups if Needed
QB recorded · $6K — seg 88: $3K, seg 93: $830 · PSE&G, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Jun 2, 2025 P2
Mon Photos 12:30pm
Tue Driveway Pour
Wed Landscaping / Pool
Thu Landscaping / Pool
Fri Landscaping / Pool
QB recorded · $34K — seg 13: $9K, seg 72: $7K · Ashpa Management, Blue Ridge Lumber — transaction dates may not match exact work timing
Week of Apr 28, 2025 P2
Mon Spindle Install (Afternoon)
Tue Paint / Shoe Molding / Balcony Railings Arrive
Wed Paint / Balcony Railing Install
Thu Appliances Arrive
Fri Appliance Install / Paint
QB recorded · $42K — seg 13: $12K, seg 14: $5K · Jaeger Lumber, Blue Ridge Lumber — transaction dates may not match exact work timing
Week of Apr 21, 2025 P2
Mon Finish Floors / Siding
Tue Finish Floors / Siding
Wed Finish Floors / Siding
Thu Finish Floors / Siding
Fri Finish Floors / Siding
QB recorded · $26K — seg 75: $8K, seg 71: $5K · Jaeger Lumber, Fabian's Painting LLC — transaction dates may not match exact work timing
Week of Apr 14, 2025 P2
Mon Tile Install / Alberto Install Deck Pavers
Tue Tile Install / Prep for Fiberglass
Wed Finish 1st Coat Paint / Tile Install / Fiberglass Deck
Thu Tile / Start Siding (Weather Permitting)
Fri Finish the Floors / Start Siding (Weather Permitting)
QB recorded · $18K — seg 58: $13K, seg 52: $1K · Jaeger Lumber, Township of Montclair — transaction dates may not match exact work timing
Week of Apr 7, 2025 P2
Mon Paint Prep
Tue Paint Prep
Wed Paint Prep
Thu Paint Prep / Tile Pick Up? (Ritchie Confirm)
Fri Paint Prep / Tile Pick Up? (Ritchie Confirm)
QB recorded · $14K — seg 73: $6K, seg 71: $3K · J & M Contractors LLC, Shades of Light — transaction dates may not match exact work timing
Week of Mar 31, 2025 P2
Mon Pick up Front Porch Material (Jefferson Lumber) / Backsplash Tile Arrives
Tue Deck Framing Inspection 8am-1pm / Post and Railing Install
Wed Decking and Tile Install
Thu Decking and Tile Install
Fri Decking and Tile Install
QB recorded · $29K — seg 13: $11K, seg 71: $6K · Standard Tile, Jaeger Lumber — transaction dates may not match exact work timing
Week of Mar 24, 2025 P2
Mon Trim, Cabinet, & Door Install
Tue Trim, Cabinet, & Door Install
Wed Trim, Cabinet, & Door Install
Thu Trim, Cabinet, & Door Install
Fri Paint Prep
QB recorded · $18K — seg 74: $7K, seg 82: $5K · Jaeger Lumber, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Mar 17, 2025 P2
Mon Non-Master Sinks and Farm Sink Arrive
Tue Interior Doors Arrive
Wed Trim, Cabinet, & Door Install
Thu Trim, Cabinet, & Door Install
Fri Trim, Cabinet, & Door Install
QB recorded · $17K — seg 74: $12K, seg 73: $1K · Jaeger Lumber, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Mar 10, 2025 P2
Mon Cabinets Arrive
Tue Trim & Cabinet Install
Wed Trim & Cabinet Install
Thu Interior Doors Arrive
Fri Trim, Cabinet, & Door Install
QB recorded · $17K — seg 73: $9K, seg 63: $5K · Jaeger Lumber, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Mar 3, 2025 P1
Mon Flooring Install Begins
Tue Flooring Install
Wed Flooring Install
Thu Flooring Install
Fri Trim and Interior Doors Arrive
QB recorded · $23K — seg 13: $8K, seg 74: $7K · Jaeger Lumber, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Feb 24, 2025 P1
Mon Spackle
Tue Spackle / Flooring Delivery
Wed Spackle
Thu Flooring Install
Fri Flooring Install
QB recorded · $15K — seg 64: $6K, seg 69: $5K · Jaeger Lumber, Blue Ridge Lumber — transaction dates may not match exact work timing
Week of Feb 17, 2025 P1
Mon Sheetrock Install
Tue Sheetrock Install
Wed Spackle
Thu Flooring Delivery / Spackle
Fri Spackle
QB recorded · $8K — seg 69: $5K, seg 52: $1K · Ashpa Management, Elite Drywall Contracting LLC — transaction dates may not match exact work timing
Week of Feb 10, 2025 P1
Mon Insulation Inspection 8-1pm
Tue Prep For Sheetrock Install
Wed Sheetrock Delivery (weather permitting)
Thu Sheetrock Install / Delivery (weather permitting)
Fri Sheetrock Install
QB recorded · $40K — seg 52: $18K, seg 63: $11K · Bergen-Essex Contractors Inc, Yover Tenezaca (Plumber) — transaction dates may not match exact work timing
Week of Feb 3, 2025 P1
Mon Roughs
Tue Rough Electric, Plumbing, and Gas Inspections 8-1pm
Wed Ductwork and Framing Inspections 8-1pm
Thu Install Insulation
Fri Install Insulation
QB recorded · $19K — seg 13: $8K, seg 67: $3K · Jaeger Lumber, Home Depot — transaction dates may not match exact work timing
Week of Dec 30, 2024 P1
Mon Interior Stairs Arrive
Tue Stair Install / PVC Plumbing
Wed HVAC Begins
Thu HVAC
Fri HVAC
QB recorded · $11K — seg 13: $10K, seg 56: $702 · Ashpa Management, Jaeger Lumber — transaction dates may not match exact work timing
Week of Dec 23, 2024 P1
Mon PVC Plumbing
Tue PVC Plumbing
Wed PVC Plumbing
Thu PVC Plumbing
Fri HVAC Begins
QB recorded · $29K — seg 52: $28K, seg 13: $943 · Blue Ridge Lumber, Jaeger Lumber — transaction dates may not match exact work timing
Week of Dec 16, 2024 P1
Mon PVC Plumbing
Tue PVC Plumbing
Wed PVC Plumbing
Thu PVC Plumbing
Fri PVC Plumbing
QB recorded · $2K — seg 56: $2K, seg 52: $255 · Jaeger Lumber, J and R Railings Inc. — transaction dates may not match exact work timing
Week of Dec 9, 2024 P1
Mon PVC Plumbing
Tue PVC Plumbing
Wed PVC Plumbing
Thu PVC Plumbing
Fri PVC Plumbing / HVAC Begins
Week of Dec 2, 2024 P1
Mon Award Roughs / Window Install
Tue Award Roughs / Window Install
Wed PVC Plumbing / Window Install
Thu PVC Plumbing
Fri PVC Plumbing
QB recorded · $101K — seg UNKNOWN: $96K, seg 53: $4K · Ashpa Management, Eduar Raudales — transaction dates may not match exact work timing
Week of Nov 25, 2024
Mon Roof Install / Award Roughs
Tue Roof Install / Award Roughs
Wed PVC Plumbing / Windows Arrive
Thu PVC Plumbing / Window Install
Fri PVC Plumbing / Window Install
QB recorded · $33K — seg 54: $23K, seg 13: $10K · Blue Ridge Lumber, Staples — transaction dates may not match exact work timing
Week of Nov 18, 2024
Mon Framing
Tue Framing
Wed Roof Install / Framing
Thu Roof Install / Framing
Fri Roof Install / Framing
QB recorded · $10K — seg 53: $5K, seg 63: $4K · Ashpa Management, WaterWays Decor — transaction dates may not match exact work timing
Week of Nov 11, 2024
Mon Roof Install / Framing
Tue Roof Install / Framing
Wed Roof Install / Framing
Thu Roughs
Fri Roughs
QB recorded · $6K — seg 52: $6K · Bergen-Essex Contractors Inc — transaction dates may not match exact work timing
Week of Nov 4, 2024
Mon Framing
Tue Framing
Wed Framing
Thu Roof Install / Framing
Fri Roof Install / Framing
QB recorded · $2K — seg 64: $1K, seg 18: $812 · Ashpa Management, Grant Supplies — transaction dates may not match exact work timing
Week of Oct 28, 2024
Mon Framing
Tue Framing
Wed Framing
Thu Framing
Fri Framing
QB recorded · $47K — seg 52: $23K, seg 42: $12K · Bergen-Essex Contractors Inc, J & J Demo LLC — transaction dates may not match exact work timing
Week of Oct 21, 2024
Mon Slab Prep / Framing
Tue Slab and Slab Plumbing Inspection
Wed Concrete Delivery / Framing
Thu Framing
Fri Framing
QB recorded · $27K — seg 52: $25K, seg 18: $2K · Bergen-Essex Contractors Inc, Blue Ridge Lumber — transaction dates may not match exact work timing
Week of Oct 14, 2024
Mon Pour Footing Slab
Tue Window Measurements: Josh, Hector, Andrew
Wed Basement Slab Work
Thu Basement Slab Work
Fri Basement Slab Work
QB recorded · $11K — seg 32: $10K, seg 42: $996 · J & J Demo LLC, Grant Supplies — transaction dates may not match exact work timing
Week of Oct 7, 2024
Mon Finish Interior Demo / Footing Prep
Tue Finish Interior Demo / Footing Prep
Wed Footing Prep / Framing
Thu Basement slab prep / Framing
Fri Deck Footing Inspection
QB recorded · $6K — seg 88: $3K, seg 32: $2K · Ashpa Management, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Sep 30, 2024
Mon Finish Interior Demo
Tue Remove Trees / Finish Landscaping
Wed Remove Trees / Finish Landscaping
Thu Remove Trees / Finish Landscaping
Fri Begin Framing
QB recorded · $9K — seg 13: $9K · Hoffinger Yaacov, Alpha Funding Solutions (FCI LendingServices) — transaction dates may not match exact work timing
Week of Jan 29, 2024
Mon Roughs
Tue Roughs
Wed Meet Rob Onsite 10am
Week of Jan 22, 2024
Mon Roughs
Tue Roughs
Wed Roughs
Week of Jan 15, 2024
Mon PSEG to Install Smart Meter 12-4pm
Tue HVAC
Wed HVAC
Week of Jan 8, 2024
Mon HVAC Begins
Tue HVAC
Wed HVAC