1309 Graymill Completed

Scotch Plains · PM: Hector

Phase Timeline · QB spend = financial record (transaction dates may not match work timing)

P1
No baseline
P2
No baseline
P3
No baseline
PM Delay Notes Siding Roughs Stair / FP Insulation Sheetrock / Spackle Siding Roughs Fireplace Insulation Sheetrock / Spackle Siding Roughs Fireplace Insulation Sheetrock / Spackle Siding Roughs Fireplace Insulation Sheetrock / Spackle

Activity Log

Week of Jun 29, 2026
Mon New SESC PLAN by 7/10
Week of Jun 22, 2026
Mon Roughs Install
Tue Roughs Install
Wed Rough Inspections 7:30am-2pm
Thu Fire Stop / Fire Block Install
Fri Insulation Inspection?
Week of Jun 15, 2026
Mon Roughs Install
Tue Roughs Install
Wed Roughs Install
Thu Finish Silt Fence Work
Fri Roughs Install
QB recorded · $10K — seg 52: $6K, seg 64: $3K · Huston Lumber, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Jun 8, 2026
Mon Roughs Install
Tue Roughs Install
Wed Roughs Install
Thu Roughs Install
Fri Roughs Install
QB recorded · $15K — seg 62: $8K, seg 52: $5K · Buildesign Home Improvement, LLC, Staples — transaction dates may not match exact work timing
Week of Jun 1, 2026
Mon Plumbing Roughs
Tue IC Can Delivery
Wed Electric / Plumbing / HVAC Roughs
Thu Interior Stair Delivery
Fri Electric / Plumbing / HVAC Roughs
QB recorded · $23K — seg 63: $11K, seg 62: $9K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of May 25, 2026
Mon Off For Memorial Day
Tue Plumbing Roughs
Wed Plumbing Roughs
Thu Plumbing Roughs
Fri Plumbing Roughs
QB recorded · $22K — seg 52: $10K, seg 53: $5K · Blue Ridge Lumber, Jaeger Lumber — transaction dates may not match exact work timing
Week of May 18, 2026
Mon Roofing / Recessed Cans Arrive
Tue Roofing
Wed Roofing
Thu Prep For Roughs
Fri Prep For Roughs
QB recorded · $4K — seg 18: $2K, seg 52: $2K · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of May 11, 2026
Mon Window Delivery 11am
Tue Finish Roof Sheathing
Wed Roofing Install
Thu Sheathing Inspection 7:30am-2pm
Fri Window Install / Non-Master Shower Roughs Arrive
QB recorded · $52K — seg 52: $44K, seg 63: $4K · Blue Ridge Lumber, Ashpa Management — transaction dates may not match exact work timing
Week of May 4, 2026
Mon Framing
Tue Framing
Wed Framing
Thu Framing
Fri Roof Install
QB recorded · $15K — seg 53: $8K, seg 42: $4K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Apr 27, 2026
Mon 8am Concrete Truck Delivery
Tue Framing
Wed Framing
Thu Framing
Fri Windows Arrive into BRL
QB recorded · $27K — seg 52: $17K, seg 42: $5K · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Apr 20, 2026
Mon First Floor Walls, 2nd Floor Deck Framing Material Arrives
Tue Framing
Wed Attic and Roofing Framing Material Arrives
Thu Garage Slab Inspection 7:30am-2pm
Fri Framing
QB recorded · $47K — seg 52: $43K, seg 42: $2K · NJ American Water, Blue Ridge Lumber — transaction dates may not match exact work timing
Week of Apr 13, 2026
Mon Install Decking
Tue Install Decking
Wed Backfill Inspection 7:30am-2pm
Thu Backfill
Fri Backfill
QB recorded · $19K — seg 52: $18K, seg 32: $400 · Buildesign Home Improvement, LLC, Rent All Center — transaction dates may not match exact work timing
Week of Apr 6, 2026
Mon Foundation and Slab Inspection 7:30am-2pm
Tue Concrete Delivery 8am / Basement PSLs Arrive
Wed Steel Arrives / Install Decking
Thu Install Decking
Fri Decking Material Arrives
QB recorded · $34K — seg 82: $13K, seg 44: $9K · Zari Custom Homes Corporation, Blue Ridge Lumber — transaction dates may not match exact work timing
Week of Mar 30, 2026
Mon Remove Extra Dirt / Prep Gravel for Crane
Tue Remove Extra Dirt / Prep Gravel for Crane
Wed Final Prep for Superior Walls
Thu Superior Walls Set Date
Fri Prep for Slab and Foundation Inspection
QB recorded · $56K — seg 42: $28K, seg 52: $16K · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 23, 2026
Mon Superior Wall Town Inspections 7:30am-2pm
Tue Prep for Superior Walls Inspection
Wed Superior Wall Company Inspection in the AM
Thu Superior Wall Town Inspections 7:30am-2pm
Fri Make Any Modifications Superior Wall Requests
QB recorded · $36K — seg 42: $27K, seg 18: $4K · NJ American Water, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Mar 16, 2026
Mon Dirt Truck and Machine Rental
Tue Bobcat Arrives
Wed Mixed Truck Dirt Removal
Thu Dirt Removal
Fri Dirt Removal
QB recorded · $723 — seg 18: $550, seg 42: $173 · Buildesign Home Improvement, LLC, E.L. Congdon & Sons Lumber Co — transaction dates may not match exact work timing
Week of Mar 9, 2026
Mon Foundation / Slab Prep / Slab Plumbing
Tue Underground Plumbing Inspection 7:30am-2pm / Superior Walls Site Visit
Wed Foundation / Slab Prep
Thu Foundation / Block Work
Fri Foundation / Block Work
QB recorded · $4K — seg 42: $2K, seg 44: $762 · Elizabethtown Gas, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 2, 2026
Mon Excavation
Tue Excavation
Wed Foundation
Thu Foundation
Fri Foundation
QB recorded · $10K — seg 42: $9K, seg 18: $495 · Buildesign Home Improvement, LLC, Gas - Shell — transaction dates may not match exact work timing
Week of Feb 23, 2026
Mon Prep for Machine Delivery
Tue Machine Drop Off
Wed Photos of Tracking Pad due to SUSCD
Thu Excavation
Fri Excavation
QB recorded · $25K — seg 32: $12K, seg 13: $9K · Zalmen Raskin, Ashpa Management — transaction dates may not match exact work timing
Week of Feb 16, 2026
Mon Demo / Confirm Superior Walls
Tue Demo / Confirm Superior Walls
Wed Deliver Machine
Thu Excavation
Fri Excavation
QB recorded · $9K — seg 32: $7K, seg 18: $2K · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Feb 9, 2026
Mon Demo
Tue Demo
Wed Demo
Thu Demo
Fri Demo
QB recorded · $6K — seg 32: $6K, seg 18: $82 · Buildesign Home Improvement, LLC, J & J Demo LLC — transaction dates may not match exact work timing
Week of Feb 2, 2026
Mon Demo Meeting with Hector, JJ & Pablo
Tue Demo
Wed Demo
Thu Demo
Fri Demo
QB recorded · $1K — seg 14: $545, seg 42: $500 · Buildesign Home Improvement, LLC, PSE&G — transaction dates may not match exact work timing
Week of Dec 29, 2025
Mon Wait for Permits
Tue Wait for Permits
Wed Wait for Permits
Thu New Year's Day
Fri Pest Test Pick-up
QB recorded · $17K — seg 13: $16K, seg 20: $450 · Zalmen Raskin, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Dec 22, 2025
Mon Wait for Permits
Tue Wait for Permits
Wed Wait for Permits
Thu Christmas
Fri Pest Drop
QB recorded · $304 — seg 16: $267, seg 18: $38 · Buildesign Home Improvement, LLC, Cooper Pest Solutions — transaction dates may not match exact work timing
Week of Dec 15, 2025
Mon Finish Asbestos Remediation
Tue Wait on State Report -> Submit Permits to Township -> Wait for Permits
QB recorded · $7K — seg 32: $6K, seg 16: $2K · Buildesign Home Improvement, LLC, NJ American Water — transaction dates may not match exact work timing
Week of Dec 8, 2025
Mon Asbestos Remediation
Tue Asbestos Remediation
Wed Asbestos Remediation
QB recorded · $4K — seg 32: $2K, seg 16: $2K · Elizabethtown Gas, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Dec 1, 2025
Mon Start Topo Survey
Wed Finish Topo Survey
Thu Asbestos Remediation
Fri Asbestos Remediation
QB recorded · $920 — seg 14: $920 · Township of Scotch Plains, PSE&G — transaction dates may not match exact work timing
Week of Oct 13, 2025
Mon Asbestos
QB recorded · $5K — seg 88: $4K, seg 32: $330 · NJ American Water, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Oct 6, 2025
Mon Remove Suspicious Materials
Tue Remove Suspicious Materials
Wed Asbestos Testing (outside vendor)
Thu Pest Trap Pick up (outside vendor)
QB recorded · $153K — seg 13: $75K, seg UNKNOWN: $75K · A MAC Asbestos Removal Inc, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Jul 4, 2025
Fri 4th of July
QB recorded · $14K — seg 13: $14K · Zalmen Raskin, Cohen David & Andrea — transaction dates may not match exact work timing
Week of Jan 28, 2025
Tue Demo
Wed Demo
Thu Temp Electric Inspection 3:30pm-6:30pm
QB recorded · $8K — seg 13: $8K · Zalmen Raskin, Cohen David & Andrea — transaction dates may not match exact work timing
Week of Jan 6, 2025
Mon Jose Wire Temp Service
Tue Wait on Permits
Wed Wait on Permits
Thu Wait on Permits