185 Fernwood Active P2

Montclair · PM: Hector

Phase Timeline · QB spend = financial record (transaction dates may not match work timing)

P1
P1
Done ✓ · on schedule
P2
Done ✓ · 407d behind
P3
Done ✓ · 346d behind
PM Delay Notes Exterior / Interior (Brute) Sprinkler System Plans Tree Removal Siding Flooring Trim, Tiles, Cabinets Exterior / Interior (Brute) Sprinkler System Plans Tree Removal Siding Flooring Trim, Tiles, Cabinets Exterior / Interior (Brute) Sprinkler System Plans Tree Removal Siding Flooring (basement and finished herringbone) Trim, Tiles, Cabinets Exterior / Interior (Brute) Sprinkler System Plans Tree Removal Siding Flooring (basement and finished herringbone) Trim, Tiles, Cabinets

Activity Log

Week of Jun 29, 2026 P3
Mon Extra Kitchen Window Arrives?
Week of Jun 22, 2026 P3
Mon Tile Install
Tue Flooring / Tile Install
Wed Flooring / Tile Install
Thu Flooring / Tile Install
Fri Herrinbone Flooring Arrives
Week of Jun 15, 2026 P3
Mon Flooring Delivery
Tue Tile Install
Wed Tile Install
Thu Tile Install
Fri Tile Install
QB recorded · $127K — seg UNKNOWN: $114K, seg 53: $4K · Buildesign Home Improvement, LLC, YF Interior — transaction dates may not match exact work timing
Week of Jun 8, 2026 P3
Mon Tile Prep / IT Install / Extra Kitchen Window Arrives?
Tue Tile Prep / IT Install
Wed Tile Prep / IT Install
Thu Tile Prep
Fri Tile Prep
QB recorded · $66K — seg 13: $17K, seg 71: $15K · Buildesign Home Improvement, LLC, Standard Tile — transaction dates may not match exact work timing
Week of Jun 1, 2026 P3
Mon Spackle
Tue Spackle / Hector Meet IT Vendor 12pm
Wed Sanding Spackle
Thu Floor Delivery
Fri Extra Kitchen Window Arrives to BRL
QB recorded · $17K — seg 69: $14K, seg 18: $2K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of May 25, 2026 P3
Mon Sheetrock Delivery / Fireplace Install
Tue Sheetrock Install
Wed Sheetrock Install
Thu Spackle
Fri Spackle
QB recorded · $56K — seg 69: $15K, seg 62: $12K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of May 18, 2026 P3
Mon Install Insulation
Tue Install Insulation
Wed Insulation Inspection & Gas Pressure Test 8am-1pm
Thu Sheetrock Delivery
Fri Sheetrock Install
QB recorded · $146K — seg UNKNOWN: $120K, seg 62: $12K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of May 11, 2026 P3
Mon Roughs
Tue Roughs
Wed Rough Inspections 8am-1pm
Thu Fire Stop + Fire Block
Fri Framing Inspection 8am-1pm
QB recorded · $35K — seg 62: $10K, seg 63: $10K · Jaeger Lumber, PSE&G — transaction dates may not match exact work timing
Week of May 4, 2026 P3
Mon Roofing / Roughs
Tue Insurance Inspection 1:45pm-2:30pm
Wed Roofing / Roughs
Thu Roughs
Fri Roughs
QB recorded · $32K — seg 52: $10K, seg 64: $8K · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Apr 27, 2026 P3
Mon Eyebrow Window Arrives
Tue Shingles Arrive
Wed Roofing / Roughs
Thu Roofing / Roughs
Fri Roofing / Roughs
QB recorded · $66K — seg 52: $23K, seg UNKNOWN: $19K · Ashpa Management, Jaeger Lumber — transaction dates may not match exact work timing
Week of Apr 20, 2026 P3
Mon Attic Framing / All Roughs
Tue Attic Framing / All Roughs
Wed Attic Framing / All Roughs
Thu Attic Framing / All Roughs
Fri Eyebrow Window Arrives at BRL
QB recorded · $99K — seg UNKNOWN: $86K, seg 52: $9K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Apr 13, 2026 P3
Mon Attic Framing / Electric / Plumbing
Tue Attic Framing / Electric / Plumbing
Wed HVAC Begin
Thu Attic Framing / All Roughs
Fri Attic Framing / All Roughs
QB recorded · $14K — seg 52: $10K, seg 18: $2K · PSE&G, Jaeger Lumber — transaction dates may not match exact work timing
Week of Apr 6, 2026 P3
Mon Fix Subfloor / Back Deck Framing / Plumbing / Electric
Tue Fix Subfloor / Back Deck Framing / Plumbing / Electric
Wed Fix Subfloor / Back Deck Framing / Plumbing / Electric
Thu Fix Subfloor / Back Deck Framing / Plumbing / Electric
Fri Fix Subfloor / Back Deck Framing / Plumbing / Electric
QB recorded · $19K — seg 64: $9K, seg 52: $7K · Jaeger Lumber, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 30, 2026 P3
Mon Tubs Arrive
Tue Roughs Arrive
Wed Plumbing / Aesthetic + Subfloor Framing
Thu Plumbing / Aesthetic + Subfloor Framing
Fri Plumbing / Aesthetic + Subfloor Framing
QB recorded · $29K — seg 13: $15K, seg 52: $10K · Jaeger Lumber, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 23, 2026 P3
Mon Windows Arrive (eyebrow window 4/24)
Tue Window Install / Framing / Porch Framing
Wed Window Install / Framing / Porch Framing
Thu Window Install / Framing / Porch Framing
Fri Plumbing / Framing / Porch Framing
QB recorded · $75K — seg 54: $52K, seg 52: $13K · Blue Ridge Lumber, Jaeger Lumber — transaction dates may not match exact work timing
Week of Mar 16, 2026 P3
Mon House Framing
Tue 1pm Architect Meeting with Hector
Wed House Framing & Porch Footings
Thu Plumbing / House Framing & Porch Footings
Fri Pier Footing Inspection 8am-10pm
QB recorded · $9K — seg 52: $7K, seg 18: $1K · Jaeger Lumber, Ashpa Management — transaction dates may not match exact work timing
Week of Mar 9, 2026 P3
Mon House Framing
Tue House Framing
Wed House Framing
Thu House Framing
Fri House Framing
QB recorded · $17K — seg 52: $15K, seg 18: $1K · Jaeger Lumber, Ashpa Management — transaction dates may not match exact work timing
Week of Mar 2, 2026 P3
Mon House & Garage Framing
Tue House & Garage Framing
Wed House & Garage Framing
Thu House & Garage Framing
Fri House & Garage Framing
QB recorded · $87K — seg UNKNOWN: $66K, seg 13: $15K · Jaeger Lumber, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Feb 23, 2026 P3
Mon Framing
Tue Framing
Wed Framing
Thu Framing
Fri Framing
QB recorded · $24K — seg 52: $12K, seg 18: $5K · Jaeger Lumber, Ashpa Management — transaction dates may not match exact work timing
Week of Feb 16, 2026 P3
Mon Framing / Subfloor Removal
Tue Framing / Subfloor Removal
Wed Framing / Subfloor Removal
Thu Framing
Fri Framing
QB recorded · $19K — seg 52: $15K, seg 18: $3K · Jaeger Lumber, Ashpa Management — transaction dates may not match exact work timing
Week of Feb 9, 2026 P3
Mon Framing
Tue Framing
Wed Framing
Thu Framing
Fri Framing
QB recorded · $3K — seg 52: $2K, seg 18: $1K · Jaeger Lumber, PSE&G — transaction dates may not match exact work timing
Week of Feb 2, 2026 P3
Mon Framing
Tue Framing / Measure Roof + Siding
Wed Framing
Thu Framing
Fri Framing / Measure Interior Stairs
QB recorded · $20K — seg 13: $15K, seg 52: $4K · Jaeger Lumber, Ashpa Management — transaction dates may not match exact work timing
Week of Dec 29, 2025 P3
Mon Order Bolts, Nuts, Washers, PSLS
Tue Install Trench Utilities / Clean for Framing
Wed Install Trench Utilities / Clean for Framing
Thu New Year's Day
Fri Install Trench Utilities / Clean for Framing
QB recorded · $42K — seg 13: $20K, seg 52: $16K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Dec 22, 2025 P3
Mon Remove the Machine (Without the Stairs)
Tue Remove the Machine (With the Stairs)
Wed 10am Concrete Truck / Exterior Pier Inspection 8-1pm
Thu Christmas
Fri Dig Exterior Footings and Install Trench Utilities
QB recorded · $21K — seg 52: $19K, seg 32: $2K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Dec 15, 2025 P3
Mon 8am Concrete Truck
Tue Machine Arrives
Wed Demo Block Rooms
Thu Demo Block Rooms
Fri Clean up Debris + Dig Garage Trench
QB recorded · $10K — seg 32: $9K, seg 52: $394 · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Dec 8, 2025 P3
Mon Crawl Space Footing
Tue Crawl Space Footing
Wed Interior Footing & Underground Plumbing Inspections 8-1pm
Thu Finish French Drain
Fri Finish French Drain
QB recorded · $2K — seg 62: $1K, seg 42: $838 · Buildesign Home Improvement, LLC, PSE&G — transaction dates may not match exact work timing
Week of Dec 1, 2025 P3
Mon Sheet Drain Arrives / Underground Plumbing
Tue French Drain
Wed Exterior Footings
Thu Exterior Footings
Fri Exterior Footings
QB recorded · $29K — seg 13: $14K, seg 16: $13K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Nov 24, 2025 P3
Mon Foundation Work
Tue Foundation Work
Wed Foundation Work
Thu Thanksgiving Day
Fri Foundation Work
QB recorded · $12K — seg 13: $5K, seg 42: $3K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Nov 17, 2025 P3
Mon Hector, JJ, Andrew Review Garage Trench
Tue Foundation Work
Wed Foundation Work
Thu Foundation Work
Fri Foundation Work
QB recorded · $248 — seg 18: $248, seg 16: $0 · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Nov 10, 2025 P3
Mon Finalize Foundation Plan
Tue Foundation Work
Wed Foundation Work
Thu Foundation Work
Fri Foundation Work
QB recorded · $5K — seg 32: $5K, seg 14: $201 · PSE&G, Staples — transaction dates may not match exact work timing
Week of Nov 3, 2025 P3
Mon Extra Demo Items / Price out Framing + Foundation
Tue Extra Demo Items / Price out Framing + Foundation
Wed Extra Demo Items / Price out Framing + Foundation
Thu Extra Demo Items / Price out Framing + Foundation
Fri Extra Demo Items / Price out Framing + Foundation
QB recorded · $14K — seg 13: $14K, seg 14: $100 · A-R General Contractor_Alberto Landscape & Snow Removal, Alpha Funding Solutions (FCI LendingServices) — transaction dates may not match exact work timing
Week of Oct 27, 2025 P3
Mon Extra Demo Items / Price out Framing + Foundation
Tue Extra Demo Items / Price out Framing + Foundation
Wed Extra Demo Items / Price out Framing + Foundation
Thu Extra Demo Items / Price out Framing + Foundation
Fri Extra Demo Items / Price out Framing + Foundation
QB recorded · $22K — seg 14: $16K, seg 13: $5K · Buildesign Home Improvement, LLC, Township of Montclair — transaction dates may not match exact work timing
Week of Oct 20, 2025 P3
Mon Extra Demo Items / Price out Framing + Foundation
Tue Extra Demo Items / Price out Framing + Foundation
Wed Extra Demo Items / Price out Framing + Foundation
Thu Extra Demo Items / Price out Framing + Foundation
Fri Extra Demo Items / Price out Framing + Foundation
QB recorded · $112 — seg 18: $112 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Oct 13, 2025 P3
Mon Extra Demo Items / Price out Framing Mats + Labor
Tue Extra Demo Items / Price out Framing Mats + Labor
Wed Extra Demo Items / Price out Framing Mats + Labor
Thu Extra Demo Items / Price out Framing Mats + Labor
Fri Extra Demo Items / Price out Framing Mats + Labor
QB recorded · $111 — seg 14: $111 · Township of Montclair, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Oct 6, 2025 P3
Mon Extra Demo Items / Price out Framing Mats + Labor
Tue Extra Demo Items / Price out Framing Mats + Labor
Wed Extra Demo Items / Price out Framing Mats + Labor
Thu Extra Demo Items / Price out Framing Mats + Labor
Fri Extra Demo Items / Price out Framing Mats + Labor
QB recorded · $6K — seg 16: $6K, seg 14: $201 · PSE&G, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Sep 29, 2025 P3
Mon Extra Demo Items / Price out Framing Mats + Labor
Tue Extra Demo Items / Price out Framing Mats + Labor
Wed Extra Demo Items / Price out Framing Mats + Labor
Thu Extra Demo Items / Price out Framing Mats + Labor
Fri Extra Demo Items / Price out Framing Mats + Labor
QB recorded · $20K — seg 13: $19K, seg 62: $50 · Staples, PSE&G — transaction dates may not match exact work timing
Week of Sep 22, 2025 P3
Mon Interior Demo Complete
Tue Additional Interior Demo + Exterior Demo
Wed Additional Interior Demo + Exterior Demo
Thu Additional Interior Demo + Exterior Demo
Fri Additional Interior Demo + Exterior Demo
QB recorded · $16K — seg UNKNOWN: $11K, seg 16: $5K · Garfinkel Design Group LLC, Alpha Funding Solutions (FCI LendingServices) — transaction dates may not match exact work timing
Week of Sep 15, 2025 P3
Mon Interior Demo
Tue Interior Demo
Wed Interior Demo
Thu Interior Demo
Fri Interior Demo
QB recorded · $250 — seg 13: $250 · CFSI Management — transaction dates may not match exact work timing
Week of Sep 8, 2025 P3
Mon Interior Demo
Tue Interior Demo
Wed Interior Demo
Thu Interior Demo
Fri Interior Demo
QB recorded · $132 — seg 14: $132 · PSE&G — transaction dates may not match exact work timing
Week of Sep 1, 2025 P3
Mon Interior Demo
Tue Interior Demo
Wed Interior Demo
Thu Interior Demo
Fri Interior Demo
QB recorded · $18K — seg 13: $14K, seg 16: $4K · Garfinkel Design Group LLC, Alpha Funding Solutions (FCI LendingServices) — transaction dates may not match exact work timing
Week of Aug 25, 2025 P3
Mon Interior Demo
Tue Interior Demo
Wed Interior Demo
Thu Interior Demo
Fri Interior Demo
QB recorded · $3K — seg 13: $3K, seg 14: $50 · A-R General Contractor_Alberto Landscape & Snow Removal, Robert Klink — transaction dates may not match exact work timing
Week of Aug 18, 2025 P3
Mon Interior Demo
Tue Interior Demo
Wed Interior Demo
Thu Interior Demo
Fri Interior Demo
QB recorded · $75 — seg 18: $75 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Aug 11, 2025 P3
Mon Interior Demo
Tue Interior Demo
Wed Interior Demo
Thu Interior Demo
Fri Interior Demo
QB recorded · $132 — seg 14: $132 · PSE&G — transaction dates may not match exact work timing
Week of Aug 4, 2025 P3
Mon Interior Demo
Tue Interior Demo
Wed Interior Demo
Thu Interior Demo
Fri Interior Demo
QB recorded · $150 — seg 18: $150 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Jul 28, 2025 P3
Mon Hector, Pablo, Andrew Onsite in Afternoon to look at Sprinkler System
Tue Interior Demo / Sprinkler System Removal
Wed Interior Demo / Sprinkler System Removal
Thu Interior Demo / Sprinkler System Removal
Fri Interior Demo / Sprinkler System Removal
QB recorded · $17K — seg 13: $17K · Robert Klink, Alpha Funding Solutions (FCI LendingServices) — transaction dates may not match exact work timing
Week of Jul 21, 2025 P3
Mon Interior Demo / Sprinkler System Removal
Tue Interior Demo / Sprinkler System Removal
Wed Interior Demo / Sprinkler System Removal
Thu Interior Demo / Sprinkler System Removal
Fri Interior Demo / Sprinkler System Removal
QB recorded · $50 — seg 14: $50 · A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Jul 14, 2025 P3
Mon Interior Demo / Sprinkler System Removal
Tue Interior Demo / Sprinkler System Removal
Wed Interior Demo / Sprinkler System Removal
Thu Interior Demo / Sprinkler System Removal
Fri Interior Demo / Sprinkler System Removal
Week of Jul 7, 2025 P2
Mon Interior Demo / Sprinkler System Removal
Tue Interior Demo / Sprinkler System Removal
Wed Interior Demo / Sprinkler System Removal
Thu Interior Demo / Sprinkler System Removal
Fri Interior Demo / Sprinkler System Removal
QB recorded · $5K — seg 32: $5K, seg 18: $38 · Buildesign Home Improvement, LLC, J & J Demo LLC — transaction dates may not match exact work timing
Week of Jun 30, 2025 P2
Mon Interior Demo / Sprinkler System Removal
Tue Interior Demo / Sprinkler System Removal
Wed Interior Demo / Sprinkler System Removal
Thu Interior Demo / Sprinkler System Removal
Fri 4th of July
QB recorded · $17K — seg 13: $16K, seg 18: $188 · Buildesign Home Improvement, LLC, Robert Klink — transaction dates may not match exact work timing
Week of Jun 23, 2025 P2
Mon Interior Demo / Sprinkler System Removal
Tue Interior Demo / Sprinkler System Removal
Wed Interior Demo / Sprinkler System Removal
Thu Interior Demo / Sprinkler System Removal
Fri Interior Demo / Sprinkler System Removal
QB recorded · $38 — seg 18: $38 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Jun 16, 2025 P2
Mon Interior Demo / Sprinkler System Removal
Tue Interior Demo / Sprinkler System Removal
Wed Interior Demo / Sprinkler System Removal
Thu Interior Demo / Sprinkler System Removal
Fri Interior Demo / Sprinkler System Removal
QB recorded · $76K — seg UNKNOWN: $75K, seg 88: $800 · A-R General Contractor_Alberto Landscape & Snow Removal, Alpha Funding Solutions (FCI LendingServices) — transaction dates may not match exact work timing
Week of Jun 9, 2025 P2
Mon Interior Demo
Tue Interior Demo
Wed Submit Sprinkler Letter
Thu Interior Demo
Fri Interior Demo
QB recorded · $2K — seg 14: $2K, seg 13: $250 · Buildesign Home Improvement, LLC, PSE&G — transaction dates may not match exact work timing
Week of Jun 2, 2025 P2
Mon Interior Demo
Tue Interior Demo
Wed Interior Demo
Thu Interior Demo
Fri Interior Demo
QB recorded · $100K — seg UNKNOWN: $50K, seg 13: $50K — transaction dates may not match exact work timing
Week of Jan 27, 2025
Mon Backfill Trench / Framing
Tue Framing
Wed Framing
Thu Framing
Week of Jan 20, 2025
Mon Framing
Tue Framing
Wed Underground Plumbing Inspection 8-1pm
Thu Backfill Trench / Framing
Week of Jan 13, 2025
Mon Framing / Utility Trench Install
Tue Electric and Plumbing Trench Inspections 8-1pm
Wed Framing / Utility Trench Backfill
Thu Framing / Utility Trench Backfill
Week of Jan 6, 2025
Mon Steel Arrives
Tue Andrew Meet City Inspector 10am / Utility Trench Install
Wed Framing / Utility Trench Install
Thu Framing / Utility Trench Install
QB recorded · $6K — seg 63: $6K · Yover Tenezaca (Plumber) — transaction dates may not match exact work timing