Activity Log
Mon
Video + Drone 3:30pm (Bryan)
Tue
Touch ups
Wed
Touch ups
Thu
CLOSING
QB recorded · $6.84M
— seg UNKNOWN: $4.46M, seg 99: $2.25M · NJ American Water, J & M Contractors LLC — transaction dates may not match exact work timing
Mon
Final Plumbing/Mechanical Inspection 10am-2pm
Tue
Punchlist
Wed
Final Building Inspection 7:30am-2pm
Thu
Video + Drone 3:30pm (Bryan)
Fri
Photos 11am / Punchlist
QB recorded · $15K
— seg 63: $9K, seg 76: $3K · Yover Tenezaca (Plumber), Tor Glass — transaction dates may not match exact work timing
Mon
Final Electric, Plumbing, Mechanical Inspections 9am-2pm
Tue
Final Fire Inspection 8am-11am / Smoke Cert Inspection
Wed
Pending Final Building Inspection Date
Thu
Driveway Pour (Outside Vendor)
Fri
Pending Final Building Inspection Date
QB recorded · $71K
— seg UNKNOWN: $48K, seg 75: $11K · Jose Moreno (Electrician), Elizabethtown Gas — transaction dates may not match exact work timing
Mon
Painting / Wallpaper / Install Finishes
Tue
Gas Meter Unlock 12-4pm / Painting / Wallpaper / Install Finishes
Wed
Driveway Pour (Outside Vendor)
Thu
Fireplace Install (Ernie)
Fri
Appraiser Onsite 11:30am / Island countertop Install / FINISH TODAY
QB recorded · $18K
— seg 82: $8K, seg 54: $3K · PSE&G, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Exterior Stair Install / Plumbing + Electric Finishes
Tue
Gutter Install
Wed
Gutter Install / Post, Spindle, Railing Install
Thu
Post, Spindle, Railing Install
Fri
Laundry Unit Delivery and Install (Outside Vendor)
QB recorded · $60K
— seg 13: $22K, seg 73: $13K · Buildesign Home Improvement, LLC, Home Depot — transaction dates may not match exact work timing
Mon
Island Countertop Install (Outside Vendor)
Tue
Porch Columns Arrive / Surveyors Onsite 11am-2pm
Wed
Decking Install
Thu
Decking Install
Fri
Kitchen Appliance Install and Finish Kitchen Cabinetry (Outside Vendor)
QB recorded · $13K
— seg 64: $5K, seg 74: $2K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Mon
Pantry Crown Delivery in Afternoon
Tue
Painting / Landscaping
Wed
Painting / Landscaping
Thu
Painting / Landscaping
Fri
Painting / Landscaping
QB recorded · $58K
— seg 82: $25K, seg 63: $11K · Buildesign Home Improvement, LLC, Home Depot — transaction dates may not match exact work timing
Mon
Pick Up Cabinet Accessories (Lakewood)
Tue
Belgian Block Install, Cabinet Install, Paint
Wed
Paver Install, Cabinet Install, Paint
Thu
Paver Install, Cabinet Install, Paint
Fri
Backsplash Install, Paint
QB recorded · $94K
— seg UNKNOWN: $75K, seg 75: $14K · Elizabethtown Gas, PSE&G — transaction dates may not match exact work timing
Mon
Backsplash Install / Paint / Cabinet Install
Tue
Backsplash Install / Paint / Cabinet Install
Wed
Paver Install / Paint / Hector + Andrew 2pm Site Visit
Thu
Paver Install / Paint
Fri
Paver Install / Paint
QB recorded · $88K
— seg UNKNOWN: $50K, seg 13: $22K · Township of Scotch Plains, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Kitchen and Dinette Countertop Install by Client
Tue
Backsplash Install / Cabinet Pick up
Wed
Backsplash Install / Cabinet Install / Surveryors Onsite
Thu
Paint Prep
Fri
Laundry Room Machine Install by Client
QB recorded · $13K
— seg 75: $5K, seg 64: $5K · NJ American Water, Ashpa Management — transaction dates may not match exact work timing
Mon
Cabinet Pick-up / Basement Columns, Back Deck Joists 12" OC, Sprinkler Line, Garage Steps
Tue
Verizon Install by Client
Wed
Cabinet Install, Basement columns, back deck joists 12" OC, Sprinkler Line, Garage Steps
Thu
Cabinet Install, Basement columns, back deck joists 12" OC, Sprinkler Line, Garage Steps
Fri
Cabinet Install, Basement columns, back deck joists 12" OC, Sprinkler Line, Garage Steps
QB recorded · $81K
— seg UNKNOWN: $75K, seg 63: $2K · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Cabinet Install / Stone Templating / Paint Prep
Tue
Cabinet Install / Stone Templating / Paint Prep
Wed
Cabinet Install / Stone Templating / Paint Prep
Thu
Cabinet Install / Stone Templating / Paint Prep
Fri
Pick up Cabinets (TBD)
QB recorded · $12K
— seg 73: $5K, seg UNKNOWN: $4K · Elizabethtown Gas, PSE&G — transaction dates may not match exact work timing
Mon
Paint Prep
Tue
Paint Prep
Wed
Coffee Bar Cabinets Arrive
Thu
Paint Prep
Fri
4th of July
QB recorded · $18K
— seg 13: $10K, seg 74: $4K · Buildesign Home Improvement, LLC, Chanan Feldman — transaction dates may not match exact work timing
Mon
Buyers Move Furniture Into Garage
Tue
Finish Trim
Wed
Cabinet Delivery
Thu
Master Bathroom Vanity Install (Outside Vendor)
Fri
Paint Prep
QB recorded · $28K
— seg 73: $16K, seg 74: $6K · Capitol Lighting, Ashpa Management — transaction dates may not match exact work timing
Mon
Master Closet / 1x3 Panel Wall / Basement Columns
Tue
Master Closet / 1x3 Panel Wall / Basement Columns
Wed
Master Closet / 1x3 Panel Wall / Basement Columns
Thu
Master Closet / 1x3 Panel Wall / Basement Columns
Fri
Decking Install? (Need to confirm order)
QB recorded · $247K
— seg UNKNOWN: $224K, seg 73: $8K · Strategic Insurance Partners (SIP), Huston Lumber — transaction dates may not match exact work timing
Mon
1x3 Panel Wall / Closet Instal
Tue
1x3 Panel Wall / Closet Instal
Wed
Closet Install
Thu
Closet Install
Fri
Closet Install
QB recorded · $17K
— seg 13: $9K, seg 74: $6K · Huston Lumber, J & M Contractors LLC — transaction dates may not match exact work timing
Mon
Door / Trim / Closet Install
Tue
Door / Trim / Closet Install
Wed
Closet Install
Thu
Closet Install
Fri
Closet Install
QB recorded · $5K
— seg 74: $3K, seg 71: $2K · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Mon
Trim & Tile Install
Tue
Trim & Tile Install
Wed
Work TBD - Pending Materials
Thu
Work TBD - Pending Materials
Fri
Work TBD - Pending Materials
QB recorded · $36K
— seg 13: $18K, seg 72: $7K · Township of Scotch Plains, General Investments LLC — transaction dates may not match exact work timing
Mon
Trim & Tile Install
Tue
Trim & Tile Install
Wed
Trim & Tile Install
Thu
Trim & Tile Install
Fri
Trim & Tile Install
QB recorded · $10K
— seg 71: $6K, seg 74: $4K · Ashpa Management, J & M Contractors LLC — transaction dates may not match exact work timing
Mon
Trim & Tile Install
Tue
Trim & Tile Install
Wed
Trim & Tile Install
Thu
Trim & Tile Install
Fri
Trim & Tile Install
QB recorded · $6K
— seg 74: $3K, seg 52: $996 · PSE&G, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Trim Materials Arrive
Tue
Trim Acclimate
Wed
Trim Acclimate
Thu
Trim Acclimate
Fri
Trim Install
QB recorded · $21K
— seg 69: $10K, seg 71: $7K · Wayne Tile, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Flooring Install / Basement Prime and Ceiling Paint
Tue
Flooring Install
Wed
Flooring Install
Thu
Kitchen Cabinets Arrive (Outside Vendor) / Trim Arrives?
Fri
Kitchen Cabinet Install (Outside Vendor) / Trim Install?
QB recorded · $52K
— seg 13: $19K, seg 74: $18K · The Tile Shop, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Prime Walls and Paint Ceilings / Spackle
Tue
Prime Walls and Paint Ceilings / Spackle
Wed
Prime Walls and Paint Ceilings / Spackle
Thu
Flooring Install
Fri
Flooring Install
QB recorded · $5K
— seg 72: $3K, seg 52: $855 · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Spackle
Tue
Spackle
Wed
Porch Framing Inspection 7:30-2pm / Bsmt Floor Delivery
Thu
Spackle
Fri
Prime Walls and Paint Ceilings
QB recorded · $6K
— seg 72: $5K, seg 69: $616 · Advanced Flooring, LLC, Home Depot — transaction dates may not match exact work timing
Mon
Spackle Begins
Tue
Spackle
Wed
Spackle
Thu
Flooring Delivery
Fri
Spackle
QB recorded · $35K
— seg 72: $32K, seg 71: $1K · All State Flooring Distributors, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Mon
Dumpster removal before 8am. Siding crew material arrives between 8-12pm
Tue
Exterior Insulation and Siding (NOT BY US) / PSEG Hook Up and Power Up
Wed
Exterior Insulation and Siding (NOT BY US) / HVAC Systems Up and Running
Thu
Exterior Insulation and Siding (NOT BY US) / Begin Spackle
Fri
Exterior Insulation and Siding (NOT BY US) / Spackle
QB recorded · $6K
— seg 69: $2K, seg 82: $2K · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
PSEG Hook Up and Power Up?
Tue
PSEG Hook Up and Power Up?
Wed
Spackle
Thu
Spackle
Fri
Spackle
QB recorded · $20K
— seg 13: $17K, seg 54: $2K · Blue Ridge Lumber, Jose Moreno (Electrician) — transaction dates may not match exact work timing
Mon
Jose Finish Electric Service Install
Tue
PSEG Hook up and Power Up
Wed
Spackle
Thu
Spackle
Fri
Spackle
QB recorded · $2K
— seg 52: $634, seg 69: $481 · Jose Moreno (Electrician), Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Finish Electric Hookup for PSEG
Tue
Spackle (Heat Permitting)
Wed
Spackle (Heat Permitting)
Thu
Spackle (Heat Permitting)
Fri
Spackle (Heat Permitting)
QB recorded · $106K
— seg UNKNOWN: $91K, seg 69: $10K · Jose Moreno (Electrician), Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Measuring Interior Doors
Tue
Sheetrock and Spackle
Wed
Sheetrock and Spackle
Thu
Sheetrock and Spackle
Fri
Sheetrock and Spackle
QB recorded · $7K
— seg 18: $3K, seg 54: $2K · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Award Insulation
Tue
Insulation
Wed
Insulation
Thu
Insulation
Fri
Insulation
QB recorded · $21K
— seg 13: $19K, seg 63: $549 · Township of Scotch Plains, General Plumbing Supply — transaction dates may not match exact work timing
Mon
Award Insulation
Tue
Insulation
Wed
Insulation
Thu
Insulation
Fri
Insulation
QB recorded · $2K
— seg 63: $1K, seg 64: $222 · Home Depot, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Award Insulation
Tue
Insulation
Wed
Insulation
Thu
Insulation
Fri
Insulation Inspection?
QB recorded · $18K
— seg 64: $9K, seg 74: $4K · Ashpa Management, Grant Supplies — transaction dates may not match exact work timing
Mon
Rough Electric and Ductwork Inspections
Tue
Prep for Framing Inspection (Fire Block and Fire Stop)
Wed
Framing and Rough Fire Inspection
Thu
Insulation
Fri
Insulation
QB recorded · $10K
— seg 64: $5K, seg 52: $3K · Ashpa Management, Jose Moreno (Electrician) — transaction dates may not match exact work timing
Mon
Framing / Electric / Plumbing / Ductwork Edits
Tue
Framing / Electric / Plumbing / Ductwork Edits
Wed
Framing / Electric / Plumbing / Ductwork Edits
Thu
Framing / Electric / Plumbing / Ductwork Edits
Fri
Framing / Electric / Plumbing / Ductwork Edits
QB recorded · $2K
— seg 52: $1K, seg 63: $392 · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Rough Inspections
Tue
Framing / Electric / Plumbing Edits
Wed
Framing / Electric / Plumbing Edits
Thu
Framing / Electric / Plumbing Edits
Fri
Framing Inspection?
QB recorded · $29K
— seg 13: $18K, seg 63: $10K · Chanan Feldman, Yover Tenezaca (Plumber) — transaction dates may not match exact work timing
Mon
Electric / HVAC / Plumbing
Tue
Electric / HVAC / Plumbing
Wed
Electric / HVAC / Plumbing
Thu
Electric / HVAC / Plumbing
Fri
Electric / HVAC / Plumbing
QB recorded · $17K
— seg 63: $11K, seg 82: $3K · J & M Contractors LLC, Ashpa Management — transaction dates may not match exact work timing
Mon
Electric / HVAC / Plumbing
Tue
Electric / HVAC / Plumbing
Wed
Electric / HVAC / Plumbing
Thu
Electric / HVAC / Plumbing
Fri
Electric / HVAC / Plumbing
QB recorded · $9K
— seg 64: $6K, seg 52: $3K · Blue Ridge Lumber, Home Depot — transaction dates may not match exact work timing
Mon
Electric / HVAC / Plumbing
Tue
Electric / HVAC / Plumbing
Wed
Electric / HVAC / Plumbing
Thu
Electric / HVAC / Plumbing
Fri
Electric / HVAC / Plumbing
QB recorded · $6K
— seg 64: $2K, seg 42: $1K · Ashpa Management, Home Depot — transaction dates may not match exact work timing
Mon
Electric / HVAC / Plumbing
Tue
Electric / HVAC / Plumbing
Wed
Electric / HVAC / Plumbing
Thu
Electric / HVAC / Plumbing
Fri
Footing Inspections
QB recorded · $26K
— seg 13: $19K, seg 54: $4K · Blue Ridge Lumber, Chanan Feldman — transaction dates may not match exact work timing
Mon
Electric / HVAC / Plumbing
Tue
Electric / HVAC / Plumbing
Wed
Electric / HVAC / Plumbing
Thu
Electric / HVAC / Plumbing
Fri
Electric / HVAC / Plumbing
QB recorded · $6K
— seg 56: $3K, seg 16: $2K · Huston Lumber, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
HVAC / Plumbing / Electric
Tue
HVAC / Plumbing / Electric
Wed
HVAC / Plumbing / Electric
Thu
HVAC / Plumbing / Electric
Fri
HVAC / Plumbing / Electric
QB recorded · $12K
— seg 52: $6K, seg 63: $3K · Staples, Home Depot — transaction dates may not match exact work timing
Mon
Exterior Basement Wall Framing
Tue
Exterior Basement Wall Framing
Wed
Ext Bsmt Framing / HVAC
Thu
Ext Bsmt Framing / HVAC
Fri
Ext Bsmt Framing / HVAC
QB recorded · $5K
— seg 52: $2K, seg 63: $2K · Staples, Home Depot — transaction dates may not match exact work timing
Mon
Basement Interior Framing
Tue
Basement Interior Framing
Wed
Basement Interior Framing
Thu
Basement Exterior Walls / PVC + HVAC
Fri
Basement Exterior Walls / PVC + HVAC
QB recorded · $23K
— seg 13: $18K, seg 96: $3K · Ashpa Management, Chanan Feldman — transaction dates may not match exact work timing
Mon
PVC Install
Tue
PVC Install / Basement Framing
Wed
PVC Install / Basement Framing / HVAC
Thu
PVC Install / Basement Framing / HVAC
Fri
PVC Install / Basement Framing / HVAC
QB recorded · $15K
— seg 42: $5K, seg 56: $3K · Jill Cohen Design, Fricker Emergency Sewer And Drain Cleaning LLC — transaction dates may not match exact work timing
Mon
Slab Prep / Framing / PVC
Tue
Slab Prep / Framing / PVC
Wed
Slab Inspection?
Thu
Concrete Truck Delivery
Fri
Backfill / Framing
QB recorded · $3K
— seg 96: $2K, seg 42: $936 · Fanwood Crushed Stone Co., Weldon Concrete — transaction dates may not match exact work timing
Mon
Garage Framing / Foundation Expansion / Plumbing
Tue
Garage Framing / Foundation Expansion / Plumbing
Wed
Garage Framing / Foundation Expansion / Plumbing
Thu
Garage Framing / Foundation Expansion / Plumbing
Fri
Garage Framing / Foundation Expansion / Plumbing
QB recorded · $4K
— seg 52: $4K · Huston Lumber, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Foundation Work / Plumbing
Tue
Foundation / Backfill Inspection
Wed
Backfill / Garage Framing / Plumbing
Thu
Garage Framing / Plumbing
Fri
Garage Framing / Plumbing
QB recorded · $997
— seg 18: $997 · Ashpa Management — transaction dates may not match exact work timing
Mon
Framing Delivery
Tue
Framing Changes
Wed
Framing Changes
Thu
Framing Changes
Fri
Framing Changes
QB recorded · $31K
— seg 13: $19K, seg 52: $12K · Ashpa Management, Huston Lumber — transaction dates may not match exact work timing
Mon
Framing Edits
Tue
Framing Edits
Wed
Framing Edits
Thu
Framing Edits
Fri
Framing Edits
QB recorded · $555
— seg 18: $755, seg 14: $-200 · Ashpa Management — transaction dates may not match exact work timing
Mon
Framing Edits
Tue
Framing Edits
Wed
Framing Edits
Thu
Framing Edits
Fri
Framing Edits
QB recorded · $2K
— seg 63: $970, seg 62: $541 · Amazon — transaction dates may not match exact work timing
Mon
Framing Edits
Tue
Framing Edits
Wed
Framing Edits
Thu
Framing Edits
Fri
Framing Edits
QB recorded · $270
— seg 54: $220, seg 14: $50 · A-R General Contractor_Alberto Landscape & Snow Removal, J & M Contractors LLC — transaction dates may not match exact work timing
Mon
Framing Edits
Tue
Framing Edits
Wed
Framing Edits
Thu
PVC Install
Fri
PVC Install
QB recorded · $4K
— seg 52: $4K · Zari Custom Homes Corporation — transaction dates may not match exact work timing
Mon
Sheetrock Install
Tue
Sheetrock Install
Wed
Sheetrock Install
QB recorded · $17K
— seg 13: $17K, seg 88: $800 · Chanan Feldman, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Mon
Sheetrock Install
Tue
Sheetrock Install
Wed
Sheetrock Install
QB recorded · $2K
— seg 32: $2K, seg 64: $600 · Jose Moreno (Electrician), AM & Sons Haulage LLC — transaction dates may not match exact work timing
Mon
Insulation Inspection 7:30-2pm
Tue
Sheetrock Delivery
Wed
Sheetrock Install
QB recorded · $11K
— seg 32: $9K, seg 52: $2K · Benchmark Excavating LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Gas, electric, and HVAC edits
Tue
Begin Insulation
Wed
Framing Inspection