1936 Parkwood Completed

Scotch Plains · PM: Herson

Phase Timeline · QB spend = financial record (transaction dates may not match work timing)

P1
P1
Done ✓ · 89d behind
P2
P2
Done ✓ · 234d behind
P3
P3
Done ✓ · 106d behind
PM Delay Notes Glass, Decking Posts, Spindles, Railings Painting Wallpaper, Finishes Glass, Decking Posts, Spindles, Railings Painting Wallpaper, Finishes Posts, Spindles, Railings Painting Painting / Wallpaper

Activity Log

Week of Sep 22, 2025 P2
Mon Video + Drone 3:30pm (Bryan)
Tue Touch ups
Wed Touch ups
Thu CLOSING
QB recorded · $6.84M — seg UNKNOWN: $4.46M, seg 99: $2.25M · NJ American Water, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Sep 15, 2025 P2
Mon Final Plumbing/Mechanical Inspection 10am-2pm
Tue Punchlist
Wed Final Building Inspection 7:30am-2pm
Thu Video + Drone 3:30pm (Bryan)
Fri Photos 11am / Punchlist
QB recorded · $15K — seg 63: $9K, seg 76: $3K · Yover Tenezaca (Plumber), Tor Glass — transaction dates may not match exact work timing
Week of Sep 8, 2025 P2
Mon Final Electric, Plumbing, Mechanical Inspections 9am-2pm
Tue Final Fire Inspection 8am-11am / Smoke Cert Inspection
Wed Pending Final Building Inspection Date
Thu Driveway Pour (Outside Vendor)
Fri Pending Final Building Inspection Date
QB recorded · $71K — seg UNKNOWN: $48K, seg 75: $11K · Jose Moreno (Electrician), Elizabethtown Gas — transaction dates may not match exact work timing
Week of Sep 1, 2025 P2
Mon Painting / Wallpaper / Install Finishes
Tue Gas Meter Unlock 12-4pm / Painting / Wallpaper / Install Finishes
Wed Driveway Pour (Outside Vendor)
Thu Fireplace Install (Ernie)
Fri Appraiser Onsite 11:30am / Island countertop Install / FINISH TODAY
QB recorded · $18K — seg 82: $8K, seg 54: $3K · PSE&G, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Aug 25, 2025 P2
Mon Exterior Stair Install / Plumbing + Electric Finishes
Tue Gutter Install
Wed Gutter Install / Post, Spindle, Railing Install
Thu Post, Spindle, Railing Install
Fri Laundry Unit Delivery and Install (Outside Vendor)
QB recorded · $60K — seg 13: $22K, seg 73: $13K · Buildesign Home Improvement, LLC, Home Depot — transaction dates may not match exact work timing
Week of Aug 18, 2025 P2
Mon Island Countertop Install (Outside Vendor)
Tue Porch Columns Arrive / Surveyors Onsite 11am-2pm
Wed Decking Install
Thu Decking Install
Fri Kitchen Appliance Install and Finish Kitchen Cabinetry (Outside Vendor)
QB recorded · $13K — seg 64: $5K, seg 74: $2K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Aug 11, 2025 P2
Mon Pantry Crown Delivery in Afternoon
Tue Painting / Landscaping
Wed Painting / Landscaping
Thu Painting / Landscaping
Fri Painting / Landscaping
QB recorded · $58K — seg 82: $25K, seg 63: $11K · Buildesign Home Improvement, LLC, Home Depot — transaction dates may not match exact work timing
Week of Aug 4, 2025 P2
Mon Pick Up Cabinet Accessories (Lakewood)
Tue Belgian Block Install, Cabinet Install, Paint
Wed Paver Install, Cabinet Install, Paint
Thu Paver Install, Cabinet Install, Paint
Fri Backsplash Install, Paint
QB recorded · $94K — seg UNKNOWN: $75K, seg 75: $14K · Elizabethtown Gas, PSE&G — transaction dates may not match exact work timing
Week of Jul 28, 2025 P2
Mon Backsplash Install / Paint / Cabinet Install
Tue Backsplash Install / Paint / Cabinet Install
Wed Paver Install / Paint / Hector + Andrew 2pm Site Visit
Thu Paver Install / Paint
Fri Paver Install / Paint
QB recorded · $88K — seg UNKNOWN: $50K, seg 13: $22K · Township of Scotch Plains, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Jul 21, 2025 P2
Mon Kitchen and Dinette Countertop Install by Client
Tue Backsplash Install / Cabinet Pick up
Wed Backsplash Install / Cabinet Install / Surveryors Onsite
Thu Paint Prep
Fri Laundry Room Machine Install by Client
QB recorded · $13K — seg 75: $5K, seg 64: $5K · NJ American Water, Ashpa Management — transaction dates may not match exact work timing
Week of Jul 14, 2025 P2
Mon Cabinet Pick-up / Basement Columns, Back Deck Joists 12" OC, Sprinkler Line, Garage Steps
Tue Verizon Install by Client
Wed Cabinet Install, Basement columns, back deck joists 12" OC, Sprinkler Line, Garage Steps
Thu Cabinet Install, Basement columns, back deck joists 12" OC, Sprinkler Line, Garage Steps
Fri Cabinet Install, Basement columns, back deck joists 12" OC, Sprinkler Line, Garage Steps
QB recorded · $81K — seg UNKNOWN: $75K, seg 63: $2K · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Jul 7, 2025 P2
Mon Cabinet Install / Stone Templating / Paint Prep
Tue Cabinet Install / Stone Templating / Paint Prep
Wed Cabinet Install / Stone Templating / Paint Prep
Thu Cabinet Install / Stone Templating / Paint Prep
Fri Pick up Cabinets (TBD)
QB recorded · $12K — seg 73: $5K, seg UNKNOWN: $4K · Elizabethtown Gas, PSE&G — transaction dates may not match exact work timing
Week of Jun 30, 2025 P2
Mon Paint Prep
Tue Paint Prep
Wed Coffee Bar Cabinets Arrive
Thu Paint Prep
Fri 4th of July
QB recorded · $18K — seg 13: $10K, seg 74: $4K · Buildesign Home Improvement, LLC, Chanan Feldman — transaction dates may not match exact work timing
Week of Jun 23, 2025 P2
Mon Buyers Move Furniture Into Garage
Tue Finish Trim
Wed Cabinet Delivery
Thu Master Bathroom Vanity Install (Outside Vendor)
Fri Paint Prep
QB recorded · $28K — seg 73: $16K, seg 74: $6K · Capitol Lighting, Ashpa Management — transaction dates may not match exact work timing
Week of Jun 16, 2025 P2
Mon Master Closet / 1x3 Panel Wall / Basement Columns
Tue Master Closet / 1x3 Panel Wall / Basement Columns
Wed Master Closet / 1x3 Panel Wall / Basement Columns
Thu Master Closet / 1x3 Panel Wall / Basement Columns
Fri Decking Install? (Need to confirm order)
QB recorded · $247K — seg UNKNOWN: $224K, seg 73: $8K · Strategic Insurance Partners (SIP), Huston Lumber — transaction dates may not match exact work timing
Week of Jun 9, 2025 P2
Mon 1x3 Panel Wall / Closet Instal
Tue 1x3 Panel Wall / Closet Instal
Wed Closet Install
Thu Closet Install
Fri Closet Install
QB recorded · $17K — seg 13: $9K, seg 74: $6K · Huston Lumber, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Jun 2, 2025 P2
Mon Door / Trim / Closet Install
Tue Door / Trim / Closet Install
Wed Closet Install
Thu Closet Install
Fri Closet Install
QB recorded · $5K — seg 74: $3K, seg 71: $2K · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Apr 28, 2025 P2
Mon Trim & Tile Install
Tue Trim & Tile Install
Wed Work TBD - Pending Materials
Thu Work TBD - Pending Materials
Fri Work TBD - Pending Materials
QB recorded · $36K — seg 13: $18K, seg 72: $7K · Township of Scotch Plains, General Investments LLC — transaction dates may not match exact work timing
Week of Apr 21, 2025 P2
Mon Trim & Tile Install
Tue Trim & Tile Install
Wed Trim & Tile Install
Thu Trim & Tile Install
Fri Trim & Tile Install
QB recorded · $10K — seg 71: $6K, seg 74: $4K · Ashpa Management, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Apr 14, 2025 P2
Mon Trim & Tile Install
Tue Trim & Tile Install
Wed Trim & Tile Install
Thu Trim & Tile Install
Fri Trim & Tile Install
QB recorded · $6K — seg 74: $3K, seg 52: $996 · PSE&G, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Apr 7, 2025 P2
Mon Trim Materials Arrive
Tue Trim Acclimate
Wed Trim Acclimate
Thu Trim Acclimate
Fri Trim Install
QB recorded · $21K — seg 69: $10K, seg 71: $7K · Wayne Tile, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 31, 2025 P1
Mon Flooring Install / Basement Prime and Ceiling Paint
Tue Flooring Install
Wed Flooring Install
Thu Kitchen Cabinets Arrive (Outside Vendor) / Trim Arrives?
Fri Kitchen Cabinet Install (Outside Vendor) / Trim Install?
QB recorded · $52K — seg 13: $19K, seg 74: $18K · The Tile Shop, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 24, 2025 P1
Mon Prime Walls and Paint Ceilings / Spackle
Tue Prime Walls and Paint Ceilings / Spackle
Wed Prime Walls and Paint Ceilings / Spackle
Thu Flooring Install
Fri Flooring Install
QB recorded · $5K — seg 72: $3K, seg 52: $855 · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 17, 2025 P1
Mon Spackle
Tue Spackle
Wed Porch Framing Inspection 7:30-2pm / Bsmt Floor Delivery
Thu Spackle
Fri Prime Walls and Paint Ceilings
QB recorded · $6K — seg 72: $5K, seg 69: $616 · Advanced Flooring, LLC, Home Depot — transaction dates may not match exact work timing
Week of Mar 10, 2025 P1
Mon Spackle Begins
Tue Spackle
Wed Spackle
Thu Flooring Delivery
Fri Spackle
QB recorded · $35K — seg 72: $32K, seg 71: $1K · All State Flooring Distributors, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Mar 3, 2025 P1
Mon Dumpster removal before 8am. Siding crew material arrives between 8-12pm
Tue Exterior Insulation and Siding (NOT BY US) / PSEG Hook Up and Power Up
Wed Exterior Insulation and Siding (NOT BY US) / HVAC Systems Up and Running
Thu Exterior Insulation and Siding (NOT BY US) / Begin Spackle
Fri Exterior Insulation and Siding (NOT BY US) / Spackle
QB recorded · $6K — seg 69: $2K, seg 82: $2K · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Feb 24, 2025 P1
Mon PSEG Hook Up and Power Up?
Tue PSEG Hook Up and Power Up?
Wed Spackle
Thu Spackle
Fri Spackle
QB recorded · $20K — seg 13: $17K, seg 54: $2K · Blue Ridge Lumber, Jose Moreno (Electrician) — transaction dates may not match exact work timing
Week of Feb 17, 2025 P1
Mon Jose Finish Electric Service Install
Tue PSEG Hook up and Power Up
Wed Spackle
Thu Spackle
Fri Spackle
QB recorded · $2K — seg 52: $634, seg 69: $481 · Jose Moreno (Electrician), Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Feb 10, 2025 P1
Mon Finish Electric Hookup for PSEG
Tue Spackle (Heat Permitting)
Wed Spackle (Heat Permitting)
Thu Spackle (Heat Permitting)
Fri Spackle (Heat Permitting)
QB recorded · $106K — seg UNKNOWN: $91K, seg 69: $10K · Jose Moreno (Electrician), Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Feb 3, 2025 P1
Mon Measuring Interior Doors
Tue Sheetrock and Spackle
Wed Sheetrock and Spackle
Thu Sheetrock and Spackle
Fri Sheetrock and Spackle
QB recorded · $7K — seg 18: $3K, seg 54: $2K · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Dec 30, 2024 P1
Mon Award Insulation
Tue Insulation
Wed Insulation
Thu Insulation
Fri Insulation
QB recorded · $21K — seg 13: $19K, seg 63: $549 · Township of Scotch Plains, General Plumbing Supply — transaction dates may not match exact work timing
Week of Dec 23, 2024 P1
Mon Award Insulation
Tue Insulation
Wed Insulation
Thu Insulation
Fri Insulation
QB recorded · $2K — seg 63: $1K, seg 64: $222 · Home Depot, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Dec 16, 2024 P1
Mon Award Insulation
Tue Insulation
Wed Insulation
Thu Insulation
Fri Insulation Inspection?
QB recorded · $18K — seg 64: $9K, seg 74: $4K · Ashpa Management, Grant Supplies — transaction dates may not match exact work timing
Week of Dec 9, 2024 P1
Mon Rough Electric and Ductwork Inspections
Tue Prep for Framing Inspection (Fire Block and Fire Stop)
Wed Framing and Rough Fire Inspection
Thu Insulation
Fri Insulation
QB recorded · $10K — seg 64: $5K, seg 52: $3K · Ashpa Management, Jose Moreno (Electrician) — transaction dates may not match exact work timing
Week of Dec 2, 2024 P1
Mon Framing / Electric / Plumbing / Ductwork Edits
Tue Framing / Electric / Plumbing / Ductwork Edits
Wed Framing / Electric / Plumbing / Ductwork Edits
Thu Framing / Electric / Plumbing / Ductwork Edits
Fri Framing / Electric / Plumbing / Ductwork Edits
QB recorded · $2K — seg 52: $1K, seg 63: $392 · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Nov 25, 2024 P1
Mon Rough Inspections
Tue Framing / Electric / Plumbing Edits
Wed Framing / Electric / Plumbing Edits
Thu Framing / Electric / Plumbing Edits
Fri Framing Inspection?
QB recorded · $29K — seg 13: $18K, seg 63: $10K · Chanan Feldman, Yover Tenezaca (Plumber) — transaction dates may not match exact work timing
Week of Nov 18, 2024 P1
Mon Electric / HVAC / Plumbing
Tue Electric / HVAC / Plumbing
Wed Electric / HVAC / Plumbing
Thu Electric / HVAC / Plumbing
Fri Electric / HVAC / Plumbing
QB recorded · $17K — seg 63: $11K, seg 82: $3K · J & M Contractors LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Nov 11, 2024 P1
Mon Electric / HVAC / Plumbing
Tue Electric / HVAC / Plumbing
Wed Electric / HVAC / Plumbing
Thu Electric / HVAC / Plumbing
Fri Electric / HVAC / Plumbing
QB recorded · $9K — seg 64: $6K, seg 52: $3K · Blue Ridge Lumber, Home Depot — transaction dates may not match exact work timing
Week of Nov 4, 2024 P1
Mon Electric / HVAC / Plumbing
Tue Electric / HVAC / Plumbing
Wed Electric / HVAC / Plumbing
Thu Electric / HVAC / Plumbing
Fri Electric / HVAC / Plumbing
QB recorded · $6K — seg 64: $2K, seg 42: $1K · Ashpa Management, Home Depot — transaction dates may not match exact work timing
Week of Oct 28, 2024 P1
Mon Electric / HVAC / Plumbing
Tue Electric / HVAC / Plumbing
Wed Electric / HVAC / Plumbing
Thu Electric / HVAC / Plumbing
Fri Footing Inspections
QB recorded · $26K — seg 13: $19K, seg 54: $4K · Blue Ridge Lumber, Chanan Feldman — transaction dates may not match exact work timing
Week of Oct 21, 2024 P1
Mon Electric / HVAC / Plumbing
Tue Electric / HVAC / Plumbing
Wed Electric / HVAC / Plumbing
Thu Electric / HVAC / Plumbing
Fri Electric / HVAC / Plumbing
QB recorded · $6K — seg 56: $3K, seg 16: $2K · Huston Lumber, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Oct 14, 2024 P1
Mon HVAC / Plumbing / Electric
Tue HVAC / Plumbing / Electric
Wed HVAC / Plumbing / Electric
Thu HVAC / Plumbing / Electric
Fri HVAC / Plumbing / Electric
QB recorded · $12K — seg 52: $6K, seg 63: $3K · Staples, Home Depot — transaction dates may not match exact work timing
Week of Oct 7, 2024 P1
Mon Exterior Basement Wall Framing
Tue Exterior Basement Wall Framing
Wed Ext Bsmt Framing / HVAC
Thu Ext Bsmt Framing / HVAC
Fri Ext Bsmt Framing / HVAC
QB recorded · $5K — seg 52: $2K, seg 63: $2K · Staples, Home Depot — transaction dates may not match exact work timing
Week of Sep 30, 2024 P1
Mon Basement Interior Framing
Tue Basement Interior Framing
Wed Basement Interior Framing
Thu Basement Exterior Walls / PVC + HVAC
Fri Basement Exterior Walls / PVC + HVAC
QB recorded · $23K — seg 13: $18K, seg 96: $3K · Ashpa Management, Chanan Feldman — transaction dates may not match exact work timing
Week of Sep 23, 2024 P1
Mon PVC Install
Tue PVC Install / Basement Framing
Wed PVC Install / Basement Framing / HVAC
Thu PVC Install / Basement Framing / HVAC
Fri PVC Install / Basement Framing / HVAC
QB recorded · $15K — seg 42: $5K, seg 56: $3K · Jill Cohen Design, Fricker Emergency Sewer And Drain Cleaning LLC — transaction dates may not match exact work timing
Week of Sep 16, 2024 P1
Mon Slab Prep / Framing / PVC
Tue Slab Prep / Framing / PVC
Wed Slab Inspection?
Thu Concrete Truck Delivery
Fri Backfill / Framing
QB recorded · $3K — seg 96: $2K, seg 42: $936 · Fanwood Crushed Stone Co., Weldon Concrete — transaction dates may not match exact work timing
Week of Sep 9, 2024 P1
Mon Garage Framing / Foundation Expansion / Plumbing
Tue Garage Framing / Foundation Expansion / Plumbing
Wed Garage Framing / Foundation Expansion / Plumbing
Thu Garage Framing / Foundation Expansion / Plumbing
Fri Garage Framing / Foundation Expansion / Plumbing
QB recorded · $4K — seg 52: $4K · Huston Lumber, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Sep 2, 2024 P1
Mon Foundation Work / Plumbing
Tue Foundation / Backfill Inspection
Wed Backfill / Garage Framing / Plumbing
Thu Garage Framing / Plumbing
Fri Garage Framing / Plumbing
QB recorded · $997 — seg 18: $997 · Ashpa Management — transaction dates may not match exact work timing
Week of Jul 29, 2024 P1
Mon Framing Delivery
Tue Framing Changes
Wed Framing Changes
Thu Framing Changes
Fri Framing Changes
QB recorded · $31K — seg 13: $19K, seg 52: $12K · Ashpa Management, Huston Lumber — transaction dates may not match exact work timing
Week of Jul 22, 2024 P1
Mon Framing Edits
Tue Framing Edits
Wed Framing Edits
Thu Framing Edits
Fri Framing Edits
QB recorded · $555 — seg 18: $755, seg 14: $-200 · Ashpa Management — transaction dates may not match exact work timing
Week of Jul 15, 2024 P1
Mon Framing Edits
Tue Framing Edits
Wed Framing Edits
Thu Framing Edits
Fri Framing Edits
QB recorded · $2K — seg 63: $970, seg 62: $541 · Amazon — transaction dates may not match exact work timing
Week of Jul 8, 2024 P1
Mon Framing Edits
Tue Framing Edits
Wed Framing Edits
Thu Framing Edits
Fri Framing Edits
QB recorded · $270 — seg 54: $220, seg 14: $50 · A-R General Contractor_Alberto Landscape & Snow Removal, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Jul 1, 2024 P1
Mon Framing Edits
Tue Framing Edits
Wed Framing Edits
Thu PVC Install
Fri PVC Install
QB recorded · $4K — seg 52: $4K · Zari Custom Homes Corporation — transaction dates may not match exact work timing
Week of Jan 29, 2024
Mon Sheetrock Install
Tue Sheetrock Install
Wed Sheetrock Install
QB recorded · $17K — seg 13: $17K, seg 88: $800 · Chanan Feldman, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Jan 22, 2024
Mon Sheetrock Install
Tue Sheetrock Install
Wed Sheetrock Install
QB recorded · $2K — seg 32: $2K, seg 64: $600 · Jose Moreno (Electrician), AM & Sons Haulage LLC — transaction dates may not match exact work timing
Week of Jan 15, 2024
Mon Insulation Inspection 7:30-2pm
Tue Sheetrock Delivery
Wed Sheetrock Install
QB recorded · $11K — seg 32: $9K, seg 52: $2K · Benchmark Excavating LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Jan 8, 2024
Mon Gas, electric, and HVAC edits
Tue Begin Insulation
Wed Framing Inspection