2154 Shackamaxon Completed

Scotch Plains · PM: Hector

Phase Timeline · QB spend = financial record (transaction dates may not match work timing)

P1
No baseline
P2
No baseline
P3
No baseline
PM Delay Notes Engineering Pit and Inspection Framing (Sheathing Inspection) Roofing Siding Roughs Engineering Pit and Inspection Framing (Sheathing Inspection) Roofing Siding Roughs Engineering Pit and Inspection Roofing Siding Rough Materials / Roughs Fireplace Engineering Pit and Inspection Roofing Siding Rough Materials / Roughs Fireplace

Activity Log

Week of Jun 29, 2026
Mon Change of Contractor for HVAC
Week of Jun 22, 2026
Mon Roof / Roughs Install
Tue Roof / Roughs Install
Wed Recessed Cans Arrive / Stair Delivery on Wednesday?
Thu Roughs Install / Stair Install
Fri Roughs Install / Stair Install
Week of Jun 15, 2026
Mon Roof & Tyvek Delivery
Tue Roofing / Tyvek Install
Wed Roofing / Tyvek Install
Thu Finish Silt Fence Work
Fri Roofing / Tyvek / Window Install
QB recorded · $12K — seg 63: $5K, seg 56: $3K · Huston Lumber, Ashpa Management — transaction dates may not match exact work timing
Week of Jun 8, 2026
Mon Sheathing Install
Tue Sheathing install
Wed Sheathing Inspection 7:30am-2pm
Thu Windows Arrive
Fri Final Framing Details
QB recorded · $9K — seg 53: $7K, seg 52: $1K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Jun 1, 2026
Mon Yossy Onsite to Measure Stairs
Tue Roof Framing / Sheathing
Wed Roof Framing / Sheathing
Thu Finish Roof Sheathing
Fri Roof Material Delivery
QB recorded · $6K — seg 52: $5K, seg 18: $878 · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of May 25, 2026
Mon Off For Memorial Day
Tue Framing
Wed Framing
Thu Framing
Fri Windows Due in to BRL
QB recorded · $6K — seg 18: $4K, seg 54: $1K · Blue Ridge Lumber, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of May 18, 2026
Mon Ceiling and Roof Material Arrives
Tue Framing
Wed Framing
Thu Sheathing and Decking Arrives
Fri Framing
QB recorded · $37K — seg 52: $37K, seg 18: $507 · Blue Ridge Lumber, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of May 11, 2026
Mon Framing
Tue Framing
Wed 2nd Floor Deck and Walls Material Arrives
Thu Framing
Fri Framing
QB recorded · $23K — seg 52: $19K, seg 42: $4K · Blue Ridge Lumber, Huston Lumber — transaction dates may not match exact work timing
Week of May 4, 2026
Mon Pending 1st Floor Walls and 2nd Floor Deck Material
Tue Garage Slab and Pier Footing Inspections 7:30am-2pm / 1st and 2nd floor PSLs Arrive
Wed Concrete Delivery 8am
Thu Pending Materials
Fri Pending 2nd Floor Walls, Ceiling, Roof Material / PSLs Arrive
QB recorded · $12K — seg 52: $8K, seg 42: $3K · Buildesign Home Improvement, LLC, Blue Ridge Lumber — transaction dates may not match exact work timing
Week of Apr 27, 2026
Mon Decking Material Arrives
Tue Install Decking
Wed Install Decking
Thu Backfill Inspection 7:30am-2pm
Fri Backfill
QB recorded · $45K — seg 42: $27K, seg 52: $13K · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Apr 20, 2026
Mon 8am Concrete Delivery - New Slab
Tue Pier Footing and Garage Slab Inspections 7:30am-2pm
Wed 8am Concrete Delivery - Piers
Thu Decking Material Delivery
Fri 11am Concrete Delivery - Piers
QB recorded · $21K — seg 52: $15K, seg 42: $4K · NJ American Water, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Apr 13, 2026
Mon Final Prep for Superior Walls
Tue Superior Walls Set Date
Wed Slab Plumbing Inspection 10am-2pm
Thu Slab Inspection 7:30am-2pm
Fri Pour Slab
QB recorded · $24K — seg 14: $11K, seg 52: $9K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Apr 6, 2026
Mon Foundation + Slab Gravel Install
Tue Install Corner Pins for Superior Walls
Wed Superior Wall and Exterior Pier Footing Inspection 7:30am-2pm
Thu Superior Wall and Exterior Pier Footing Inspection 7:30am-2pm
Fri Final Prep for Superior Walls
QB recorded · $34K — seg 42: $28K, seg 44: $5K · Elizabethtown Gas, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 30, 2026
Mon Prep for Engineering Pit
Tue Prep for Engineering Pit / Foundation + Slab Gravel Install
Wed Prep for Engineering Pit / Foundation + Slab Gravel Install
Thu Foundation + Slab Gravel Install
Fri Foundation + Slab Gravel Install
QB recorded · $7K — seg 42: $5K, seg 32: $2K · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 23, 2026
Mon Excavation
Tue Excavation
Wed Excavation
Thu Superior Wall Footings / Foundation Wall Building
Fri Superior Wall Footings / Foundation Wall Building
QB recorded · $22K — seg 42: $10K, seg 54: $4K · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 16, 2026
Mon Excavation
Tue Excavation
Wed Excavation
Thu Excavation
Fri Dirt Removal
QB recorded · $2K — seg 32: $2K, seg 18: $371 · NJ American Water, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 9, 2026
Mon Move Machine from 1309G to this site
Tue Excavation
Wed Excavation
Thu Excavation
Fri Excavation
QB recorded · $3K — seg 32: $2K, seg 18: $330 · Elizabethtown Gas, Ashpa Management — transaction dates may not match exact work timing
Week of Mar 2, 2026
Mon Demo / Clean up
Tue Demo / Clean up
Wed Demo / Clean up
Thu Excavation
Fri Excavation
QB recorded · $14K — seg 32: $14K, seg 18: $289 · Buildesign Home Improvement, LLC, J & J Demo LLC — transaction dates may not match exact work timing
Week of Feb 23, 2026
Mon Demo
Tue Demo
Wed Demo
Thu Demo
Fri Demo
QB recorded · $9K — seg 32: $8K, seg 18: $1K · J & M Contractors LLC, J & J Demo LLC — transaction dates may not match exact work timing
Week of Feb 16, 2026
Mon Disconnect Sewer Line / Cover Gas Meter / Install Silt Fence
Wed Demo
Thu Demo
Fri Demo
QB recorded · $489 — seg 18: $450, seg 14: $39 · NJ American Water, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Feb 9, 2026
Mon Disconnect Sewer Line / Cover Gas Meter / Install Silt Fence
Fri Demo
QB recorded · $2K — seg 32: $1K, seg 18: $407 · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Feb 2, 2026
Mon Disconnect Sewer Line / Cover Gas Meter / Install Silt Fence
QB recorded · $876 — seg 42: $500, seg 14: $202 · Buildesign Home Improvement, LLC, Elizabethtown Gas — transaction dates may not match exact work timing
Week of Dec 29, 2025
Mon Wait for Permits
Tue Wait for Permits
Wed Wait for Permits
Thu New Year's Day
Fri Pest Test Pick-up
QB recorded · $450 — seg 20: $450 · PSE&G — transaction dates may not match exact work timing
Week of Dec 22, 2025
Mon Wait for Permits
Tue Wait for Permits
Wed Wait for Permits
Thu Christmas
Fri Pest Drop
QB recorded · $304 — seg 16: $267, seg 18: $38 · Buildesign Home Improvement, LLC, Cooper Pest Solutions — transaction dates may not match exact work timing
Week of Dec 15, 2025
Mon Asbestos Remediation
Tue Asbestos Remediation
Wed Asbestos Remediation
Thu Wait on State Report -> Submit Permits to Township -> Wait for Permits
QB recorded · $2K — seg 32: $2K, seg 14: $39 · NJ American Water, E&V Services LLC — transaction dates may not match exact work timing
Week of Dec 10, 2025
Wed Asbestos Remediation
Thu Asbestos Remediation
Fri Asbestos Remediation
QB recorded · $775 — seg 16: $775 · Somerset Union Soil Conservation District — transaction dates may not match exact work timing
Week of Oct 13, 2025
Mon Asbestos
QB recorded · $526 — seg 32: $440, seg 14: $86 · NJ American Water, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Oct 6, 2025
Mon Remove Suspicious Materials
Tue Remove Suspicious Materials
Wed Asbestos Testing (outside vendor)
Thu Pest Trap Pick up (outside vendor)
QB recorded · $2K — seg 16: $2K, seg 88: $275 · A MAC Asbestos Removal Inc, PSE&G — transaction dates may not match exact work timing
Week of Jul 4, 2025
Fri 4th of July
Week of Jan 30, 2025
Thu Temp Electric Inspection 3:30pm-6:30pm
Week of Jan 6, 2025
Mon Jose Wire Temp Service
Tue Wait on Permits
Wed Wait on Permits
Thu Wait on Permits