P1
Done ✓ · 72d behind
P2
Done ✓ · 16d behind
P3
Done ✓ · 43d early
PM Delay Notes Exterior Demo (post permit receipt) Foundation Framing SOW Windows & Doors Front Door Exterior Demo (post permit receipt) Foundation Framing SOW Windows & Doors Front Door Exterior Demo (front porch) Foundation (slab inspection) Framing Mats / SOW Windows & Doors Front Door Exterior Demo (front porch) Foundation (slab inspection) Framing Mats / SOW Windows & Doors Front Door

Activity Log

Week of Jun 29, 2026 P2
Mon Slab Inspection
Tue Arch letter
Week of Jun 22, 2026 P2
Mon Pour Piers and Slab Prep
Tue Pour Piers and Slab Prep
Wed Slab Inspection?
Thu Pour Slab
Fri Backfill
Week of Jun 15, 2026 P2
Mon Block Install / Slab Prep
Tue Foundation and Backfill Inspections 8am-1pm
Wed Pour Slab / Backfill
Thu Pour Slab / Backfill
Fri Dirt Removal / Final Demo / Foundation Clean-out
QB recorded · $778 — seg 18: $680, seg 42: $99 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Jun 8, 2026 P1
Mon Contractor Unresponsive
Tue Insurance Inspection 11am
Wed Pour Footings
Thu Block Install
Fri Block Install
QB recorded · $496 — seg 18: $371, seg 16: $125 · Buildesign Home Improvement, LLC, Staples — transaction dates may not match exact work timing
Week of Jun 1, 2026 P1
Mon Contractor away on Emergency Repair
Tue Contractor away on Emergency Repair
Wed Fix Pier Footings as Needed
Thu Contractor Unresponsive
Fri Contractor Unresponsive
QB recorded · $248 — seg 18: $248 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of May 25, 2026 P1
Mon Off For Memorial Day
Tue Contractor Away on "Emergency Job"
QB recorded · $10K — seg 14: $9K, seg 18: $676 · Ashpa Management, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of May 18, 2026 P1
Mon Install Extra Rebar for Footing
Tue Footing Inspection 8am-1pm
Wed Rain Delay
Thu Rain Delay
Fri Rain Delay
QB recorded · $2K — seg 32: $2K, seg 18: $206 · Buildesign Home Improvement, LLC, CJK General Construction LLC — transaction dates may not match exact work timing
Week of May 11, 2026 P1
Mon Footing Prep
Tue Footing Prep
Wed Footing Prep
Thu Footing Inspection 8am-1pm
Fri Footing Edits as per Inspector Requests
QB recorded · $1K — seg 18: $1K · Ashpa Management — transaction dates may not match exact work timing
Week of May 4, 2026 P1
Mon Footing Prep
Tue Footing Prep
Wed Footing Prep
Thu Footing Prep
Fri Footing Prep
QB recorded · $8K — seg 32: $6K, seg 18: $1K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Apr 27, 2026 P1
Mon Pending Demo Contractor
Tue Pending Demo Contractor
Wed Demo Begins
Thu Demo
Fri Demo
QB recorded · $2K — seg 42: $1K, seg 32: $952 · Buildesign Home Improvement, LLC, AM & Sons Haulage LLC — transaction dates may not match exact work timing
Week of Apr 20, 2026 P1
Mon Footing Inspection (Basement) 8am-1pm
Tue Slab Plumbing Inspection 8am-1pm
Wed Footing Inspection (Basement) 8am-1pm / Concrete Pour 1pm
Thu Pending Demo Contractor
Fri Pending Demo Contractor
QB recorded · $2K — seg 18: $1K, seg 42: $325 · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Apr 13, 2026
Mon Pick up Permits
Tue Pending Demo Contractor
Wed Pending Demo Contractor
Thu Pending Demo Contractor
Fri Pending Demo Contractor
QB recorded · $534 — seg 18: $442, seg 42: $58 · Ashpa Management, PSE&G — transaction dates may not match exact work timing
Week of Apr 6, 2026
Mon Waiting On Permits
Tue Waiting On Permits
Wed Waiting On Permits
Thu Waiting On Permits
Fri Waiting On Permits
QB recorded · $7K — seg 16: $7K, seg 18: $95 · Buildesign Home Improvement, LLC, Home Depot — transaction dates may not match exact work timing
Week of Mar 30, 2026
Mon Waiting On Updated Arch Plans
Tue Waiting On Updated Arch Plans
Wed Finalize Framing Plan & Materials
Thu Framing
Fri Framing
QB recorded · $13 — seg 16: $13 · Staples — transaction dates may not match exact work timing
Week of Mar 23, 2026
Mon Waiting On Updated Arch Plans
Tue Waiting On Updated Arch Plans
Wed Finalize Framing Plan & Materials
Thu Framing
Fri Framing
QB recorded · $4K — seg 42: $4K, seg 18: $358 · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 16, 2026
Mon Finish Foundation
Tue 1:30pm Architect Meeting with Hector
Wed Finalize Framing Plan & Materials
Thu Framing
Fri Framing
QB recorded · $4K — seg 42: $3K, seg 18: $520 · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 9, 2026
Mon Foundation
Tue Foundation
Wed Foundation
Thu Foundation
Fri Foundation
QB recorded · $3K — seg 42: $3K, seg 14: $154 · PSE&G, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 2, 2026
Mon Brian pick up plans from Garfinkel
Tue Review Foundation / Framing
Wed Foundation / Framing
Thu Foundation / Framing
Fri Foundation / Framing
QB recorded · $363 — seg 16: $267, seg 18: $96 · Buildesign Home Improvement, LLC, Staples — transaction dates may not match exact work timing
Week of Feb 23, 2026
Mon Pending Updated Plans
Tue Pending Updated Plans
Wed Pending Updated Plans / Pending Permit Update
Thu Pending Updated Plans / Pending Permit Update
Fri Pending Updated Plans / Pending Permit Update
QB recorded · $2K — seg 18: $2K, seg 14: $100 · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Feb 16, 2026
Mon Clean up Interior Demo Debris
Tue Clean up Interior Demo Debris
Wed Pending Updated Plans
Thu Pending Updated Plans
Fri Pending Updated Plans
QB recorded · $11K — seg 32: $11K, seg 18: $330 · Buildesign Home Improvement, LLC, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Feb 9, 2026
Mon Interior Demo + Chimney Removal
Tue Interior Demo + Chimney Removal
Wed Interior Demo + Chimney Removal
Thu Interior Demo + Chimney Removal
Fri Interior Demo + Chimney Removal
QB recorded · $1K — seg 14: $643, seg 20: $330 · Buildesign Home Improvement, LLC, PSE&G — transaction dates may not match exact work timing
Week of Feb 2, 2026
Mon Interior Demo
Tue Interior Demo
Wed Interior Demo
Thu Interior Demo
Fri Interior Demo
QB recorded · $3K — seg 32: $3K, seg 18: $41 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Dec 29, 2025
Mon Tamper Down Hole in Driveway
Thu New Year's Day
QB recorded · $8K — seg 16: $8K, seg 18: $350 · A-R General Contractor_Alberto Landscape & Snow Removal, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Dec 22, 2025
Mon Tamper Down Hole in Driveway
Thu Christmas
QB recorded · $5K — seg 16: $5K, seg 14: $50 · A-R General Contractor_Alberto Landscape & Snow Removal, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Dec 15, 2025
Mon Backfill and Tamper Down Hole in Driveway
QB recorded · $856K — seg UNKNOWN: $856K, seg 44: $380 · Buildesign Home Improvement, LLC, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Dec 8, 2025
Mon Dig for Tank Sweep
Tue GPR Tank Scan @ 1pm
QB recorded · $859K — seg 12: $837K, seg 96: $18K · Strategic Insurance Partners (SIP), Ridge Title Agency — transaction dates may not match exact work timing
Week of Jan 27, 2025
Mon Interior Demo
Tue Interior Demo
Wed Interior Demo
Thu Interior Demo
Week of Jan 20, 2025
Mon Prep for Interior Demo
Tue Begin Interior Demo
Wed Interior Demo
Thu Interior Demo
Week of Jan 13, 2025
Mon Award Interior Demo / Submit Permits
Tue Award Interior Demo / Submit Permits
Wed Award Interior Demo / Submit Permits
Thu Award Interior Demo / Submit Permits
Week of Jan 6, 2025
Mon Price out / Award Interior Demo #'s
Tue Price out / Award Interior Demo #'s
Wed Price out / Award Interior Demo #'s
Thu Price out / Award Interior Demo #'s