Activity Log
Mon
Slab Inspection
Tue
Arch letter
Mon
Pour Piers and Slab Prep
Tue
Pour Piers and Slab Prep
Wed
Slab Inspection?
Thu
Pour Slab
Fri
Backfill
Mon
Block Install / Slab Prep
Tue
Foundation and Backfill Inspections 8am-1pm
Wed
Pour Slab / Backfill
Thu
Pour Slab / Backfill
Fri
Dirt Removal / Final Demo / Foundation Clean-out
QB recorded · $778
— seg 18: $680, seg 42: $99 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Contractor Unresponsive
Tue
Insurance Inspection 11am
Wed
Pour Footings
Thu
Block Install
Fri
Block Install
QB recorded · $496
— seg 18: $371, seg 16: $125 · Buildesign Home Improvement, LLC, Staples — transaction dates may not match exact work timing
Mon
Contractor away on Emergency Repair
Tue
Contractor away on Emergency Repair
Wed
Fix Pier Footings as Needed
Thu
Contractor Unresponsive
Fri
Contractor Unresponsive
QB recorded · $248
— seg 18: $248 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Off For Memorial Day
Tue
Contractor Away on "Emergency Job"
QB recorded · $10K
— seg 14: $9K, seg 18: $676 · Ashpa Management, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Mon
Install Extra Rebar for Footing
Tue
Footing Inspection 8am-1pm
Wed
Rain Delay
Thu
Rain Delay
Fri
Rain Delay
QB recorded · $2K
— seg 32: $2K, seg 18: $206 · Buildesign Home Improvement, LLC, CJK General Construction LLC — transaction dates may not match exact work timing
Mon
Footing Prep
Tue
Footing Prep
Wed
Footing Prep
Thu
Footing Inspection 8am-1pm
Fri
Footing Edits as per Inspector Requests
QB recorded · $1K
— seg 18: $1K · Ashpa Management — transaction dates may not match exact work timing
Mon
Footing Prep
Tue
Footing Prep
Wed
Footing Prep
Thu
Footing Prep
Fri
Footing Prep
QB recorded · $8K
— seg 32: $6K, seg 18: $1K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Mon
Pending Demo Contractor
Tue
Pending Demo Contractor
Wed
Demo Begins
Thu
Demo
Fri
Demo
QB recorded · $2K
— seg 42: $1K, seg 32: $952 · Buildesign Home Improvement, LLC, AM & Sons Haulage LLC — transaction dates may not match exact work timing
Mon
Footing Inspection (Basement) 8am-1pm
Tue
Slab Plumbing Inspection 8am-1pm
Wed
Footing Inspection (Basement) 8am-1pm / Concrete Pour 1pm
Thu
Pending Demo Contractor
Fri
Pending Demo Contractor
QB recorded · $2K
— seg 18: $1K, seg 42: $325 · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Mon
Pick up Permits
Tue
Pending Demo Contractor
Wed
Pending Demo Contractor
Thu
Pending Demo Contractor
Fri
Pending Demo Contractor
QB recorded · $534
— seg 18: $442, seg 42: $58 · Ashpa Management, PSE&G — transaction dates may not match exact work timing
Mon
Waiting On Permits
Tue
Waiting On Permits
Wed
Waiting On Permits
Thu
Waiting On Permits
Fri
Waiting On Permits
QB recorded · $7K
— seg 16: $7K, seg 18: $95 · Buildesign Home Improvement, LLC, Home Depot — transaction dates may not match exact work timing
Mon
Waiting On Updated Arch Plans
Tue
Waiting On Updated Arch Plans
Wed
Finalize Framing Plan & Materials
Thu
Framing
Fri
Framing
QB recorded · $13
— seg 16: $13 · Staples — transaction dates may not match exact work timing
Mon
Waiting On Updated Arch Plans
Tue
Waiting On Updated Arch Plans
Wed
Finalize Framing Plan & Materials
Thu
Framing
Fri
Framing
QB recorded · $4K
— seg 42: $4K, seg 18: $358 · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Finish Foundation
Tue
1:30pm Architect Meeting with Hector
Wed
Finalize Framing Plan & Materials
Thu
Framing
Fri
Framing
QB recorded · $4K
— seg 42: $3K, seg 18: $520 · Ashpa Management, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Foundation
Tue
Foundation
Wed
Foundation
Thu
Foundation
Fri
Foundation
QB recorded · $3K
— seg 42: $3K, seg 14: $154 · PSE&G, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Brian pick up plans from Garfinkel
Tue
Review Foundation / Framing
Wed
Foundation / Framing
Thu
Foundation / Framing
Fri
Foundation / Framing
QB recorded · $363
— seg 16: $267, seg 18: $96 · Buildesign Home Improvement, LLC, Staples — transaction dates may not match exact work timing
Mon
Pending Updated Plans
Tue
Pending Updated Plans
Wed
Pending Updated Plans / Pending Permit Update
Thu
Pending Updated Plans / Pending Permit Update
Fri
Pending Updated Plans / Pending Permit Update
QB recorded · $2K
— seg 18: $2K, seg 14: $100 · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Mon
Clean up Interior Demo Debris
Tue
Clean up Interior Demo Debris
Wed
Pending Updated Plans
Thu
Pending Updated Plans
Fri
Pending Updated Plans
QB recorded · $11K
— seg 32: $11K, seg 18: $330 · Buildesign Home Improvement, LLC, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Mon
Interior Demo + Chimney Removal
Tue
Interior Demo + Chimney Removal
Wed
Interior Demo + Chimney Removal
Thu
Interior Demo + Chimney Removal
Fri
Interior Demo + Chimney Removal
QB recorded · $1K
— seg 14: $643, seg 20: $330 · Buildesign Home Improvement, LLC, PSE&G — transaction dates may not match exact work timing
Mon
Interior Demo
Tue
Interior Demo
Wed
Interior Demo
Thu
Interior Demo
Fri
Interior Demo
QB recorded · $3K
— seg 32: $3K, seg 18: $41 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Tamper Down Hole in Driveway
Thu
New Year's Day
QB recorded · $8K
— seg 16: $8K, seg 18: $350 · A-R General Contractor_Alberto Landscape & Snow Removal, J & M Contractors LLC — transaction dates may not match exact work timing
Mon
Tamper Down Hole in Driveway
Thu
Christmas
QB recorded · $5K
— seg 16: $5K, seg 14: $50 · A-R General Contractor_Alberto Landscape & Snow Removal, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Backfill and Tamper Down Hole in Driveway
QB recorded · $856K
— seg UNKNOWN: $856K, seg 44: $380 · Buildesign Home Improvement, LLC, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Mon
Dig for Tank Sweep
Tue
GPR Tank Scan @ 1pm
QB recorded · $859K
— seg 12: $837K, seg 96: $18K · Strategic Insurance Partners (SIP), Ridge Title Agency — transaction dates may not match exact work timing
Mon
Interior Demo
Tue
Interior Demo
Wed
Interior Demo
Thu
Interior Demo
Mon
Prep for Interior Demo
Tue
Begin Interior Demo
Wed
Interior Demo
Thu
Interior Demo
Mon
Award Interior Demo / Submit Permits
Tue
Award Interior Demo / Submit Permits
Wed
Award Interior Demo / Submit Permits
Thu
Award Interior Demo / Submit Permits
Mon
Price out / Award Interior Demo #'s
Tue
Price out / Award Interior Demo #'s
Wed
Price out / Award Interior Demo #'s
Thu
Price out / Award Interior Demo #'s