52 Wildwood Completed

Montclair · PM: Hector

Phase Timeline · QB spend = financial record (transaction dates may not match work timing)

P1
No baseline
P2
No baseline
P3
No baseline
PM Delay Notes Foundation (Footing Inspection) Tree Removal Framing Windows & Doors (Front Door) New Construction Docs Foundation (Footing Inspection) Tree Removal Framing Windows & Doors (Front Door) Foundation Tree Removal Framing Windows & Doors (Front Door) Foundation Tree Removal Framing Windows & Doors (Front Door)

Activity Log

Week of Jun 29, 2026
Mon Arch letter (mailed to the office)
Week of Jun 22, 2026
Mon Pour Footings
Tue Pour Footings
Wed Prep Foundation Wall Forms
Thu Prep Foundation Wall Forms
Fri Prep Foundation Wall Forms
Week of Jun 15, 2026
Mon Demo Existing Foundation Walls
Tue Footing Inspection 8am-1pm
Wed Pour Footings
Thu Pour Footings
Fri Prep Foundation Wall Forms
QB recorded · $206 — seg 18: $206 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Jun 8, 2026
Mon Stop Work Order
QB recorded · $838 — seg 16: $796, seg 18: $41 · Buildesign Home Improvement, LLC, Staples — transaction dates may not match exact work timing
Week of Jun 1, 2026
Mon Stop Work Order
QB recorded · $82 — seg 18: $82 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of May 25, 2026
Mon Stop Work Order
QB recorded · $2K — seg 18: $1K, seg 14: $353 · A-R General Contractor_Alberto Landscape & Snow Removal, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of May 18, 2026
Mon Edit Excavation and Footing Prep
Tue Footing Inspection 8am-1pm
Wed Temporary Electric Service Inspection 8am-1pm
Thu Prep for Footing Re-Inspection
Fri Footing Inspection 8am-1pm
QB recorded · $465 — seg 42: $258, seg 18: $206 · Buildesign Home Improvement, LLC, E.L. Congdon & Sons Lumber Co — transaction dates may not match exact work timing
Week of May 11, 2026
Mon Footing Prep
Tue Footing Prep
Wed Footing Prep
Thu Footing Prep
Fri Footing Prep
QB recorded · $10K — seg 32: $9K, seg 18: $673 · Buildesign Home Improvement, LLC, CJK General Construction LLC — transaction dates may not match exact work timing
Week of May 4, 2026
Mon Demo
Tue Demo
Wed Excavation
Thu Excavation
Fri Footing Prep
QB recorded · $14K — seg 32: $13K, seg 18: $248 · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Apr 27, 2026
Mon Pending Demo Contractor
Tue Insurance Inspection 4-5pm
Wed Pending Demo Contractor
Thu Pending Demo Contractor
Fri Demo Begins
QB recorded · $6K — seg 32: $6K, seg 86: $390 · AM & Sons Haulage LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Apr 20, 2026
Mon Install Silt Fence
Tue Pending Demo Contractor
Wed Pending Demo Contractor
Thu Pending Demo Contractor
Fri Pending Demo Contractor
QB recorded · $1K — seg 14: $560, seg 18: $472 · Buildesign Home Improvement, LLC, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Apr 13, 2026
Mon Waiting On Permits
Tue Pick up Permits
Wed Pending Demo Contractor
Thu Pending Demo Contractor
Fri Pending Demo Contractor
QB recorded · $12K — seg 16: $11K, seg 18: $307 · Home Depot, Township of Montclair — transaction dates may not match exact work timing
Week of Apr 6, 2026
Mon Waiting On Permits
Tue Waiting On Permits
Wed Waiting On Permits
Thu Waiting On Permits
Fri Waiting On Permits
QB recorded · $44 — seg 18: $41, seg 16: $5 · Staples, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 30, 2026
Mon Waiting On Permits
Tue Waiting On Permits
Wed Waiting On Permits
Thu Waiting On Permits
Fri Waiting On Permits
QB recorded · $41 — seg 18: $41 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 23, 2026
Mon Pending Demo Permit Pick-up
QB recorded · $10K — seg 14: $10K, seg 18: $110 · J & M Contractors LLC, Northshield Insurance Services — transaction dates may not match exact work timing
Week of Mar 16, 2026
Mon Pending Demo Permit
QB recorded · $168 — seg 16: $85, seg 18: $82 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 9, 2026
Mon Pending Demo Permit
QB recorded · $824 — seg 63: $618, seg 18: $206 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 2, 2026
Mon Cut and Cap Water and Sewer Lines
Tue Cut and Cap Water and Sewer Lines
Wed Inspect Water / Sewer Line
Thu Inspect Water / Sewer Line
Fri Submit Demo Permit
QB recorded · $15 — seg 16: $15 · Staples — transaction dates may not match exact work timing
Week of Feb 23, 2026
Mon Water Dept Remove Water Meter
Tue Water Dept Remove Water Meter
Wed Water Dept Remove Water Meter
Thu Water Dept Remove Water Meter
Fri Cut and Cap Water and Sewer Lines
QB recorded · $902 — seg 18: $668, seg 44: $234 · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Feb 16, 2026
Mon Asbestos Removal
Tue Asbestos Removal
Wed Asbestos Removal
Thu Utility Disconnect
Fri Utility Disconnect
QB recorded · $10K — seg 32: $10K · MHM Restoration LLC — transaction dates may not match exact work timing
Week of Feb 9, 2026
Mon Asbestos Removal - State Notification Wait Period
Tue Asbestos Removal - State Notification Wait Period
Wed Asbestos Removal - State Notification Wait Period
Thu Asbestos Removal
Fri Asbestos Removal
QB recorded · $15 — seg 95: $15 · Gas - Gulf — transaction dates may not match exact work timing
Week of Feb 2, 2026
Mon Asbestos Removal - State Notification Wait Period
Tue Asbestos Removal - State Notification Wait Period
Wed Asbestos Removal - State Notification Wait Period
Thu Asbestos Removal - State Notification Wait Period
Fri Asbestos Removal - State Notification Wait Period
QB recorded · $4K — seg 32: $4K, seg 16: $5 · MHM Restoration LLC, Staples — transaction dates may not match exact work timing
Week of Nov 27, 2025
Thu Thanksgiving Day
QB recorded · $59 — seg 14: $59 · Township of Montclair — transaction dates may not match exact work timing
Week of Nov 13, 2025
Thu Cut and Cap Water and Sewer Lines
Fri Cut and Cap Water and Sewer Lines
QB recorded · $-237 — seg 42: $121, seg 14: $-358 · Jaeger Lumber, PSE&G — transaction dates may not match exact work timing
Week of Oct 13, 2025
Mon Asbestos
QB recorded · $50 — seg 14: $50 · A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Jan 27, 2025
Mon Asbestos Removal
Tue Asbestos Removal
Wed Asbestos Removal
Thu Asbestos Removal
QB recorded · $15K — seg 13: $14K, seg 16: $1K · Morgan Engineering & Surveying, Chanan Feldman — transaction dates may not match exact work timing
Week of Jan 20, 2025
Mon Asbestos Removal
Tue Asbestos Removal
Wed Asbestos Removal
Thu Asbestos Removal
QB recorded · $50 — seg 14: $50 · A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Jan 13, 2025
Mon Asbestos Removal
Tue Asbestos Removal
Wed Asbestos Removal
Thu Asbestos Removal