← How Every Dollar Gets Accounted For
VG Home Buyers · Cost Code Reference

Cost Code Cross-Reference Map Segments · Work Orders · Cost Codes — complete mapping

Generated 2026-05-28 Source Cost Code Unified.csv + segments.yaml + work-orders.yaml
Cost Codes
228
atomic QB line items
Segments
39
32 construction + 7 deal
Work Orders
54
per property · P1 – P3
WO → Segment
1:1
every WO maps exactly one segment
Part A — Segment Reference Grid

All 39 Segments — Budget Buckets by Number

Each segment is a budget bucket. The large number is the segment code; the badge shows how many cost codes live inside it. The small code at the bottom is the representative band code (##.0 catch-all, or earliest code if no band exists). Sorted numerically.

Construction Segments (32)
167
Project Prep
16.0 ▸
189
Site Management
18.0 ▸
2017
Site Systems
20.0 ▸
325
Demolition
32.0 ▸
424
Foundation
42.0 ▸
4412
Site Work
44.0 ▸
527
Framing
52.0 ▸
535
Roofing
53.0 ▸
544
Windows & Exterior Doors
54.0 ▸
563
Interior Stairs
56.0 ▸
5810
Siding & Shutters
58.0 ▸
627
HVAC
62.0 ▸
637
Plumbing
63.0 ▸
648
Electrical
64.0 ▸
651
Security & Technology
65.0 ▸
662
Fireplaces
66.0 ▸
678
Insulation & Soundproofing
67.0 ▸
694
Drywall
69.0 ▸
713
Tile
71.0 ▸
726
Flooring
72.0 ▸
734
Cabinetry & Countertops
73.0 ▸
7431
Interior Carpentry
74.0 ▸
758
Painting, Wallpaper & Stain
75.0 ▸
764
Accessories
76.0 ▸
773
Appliances
77.0 ▸
828
Exterior Carpentry
82.0 ▸
843
Exterior Masonry
84.0 ▸
853
Exterior Painting
85.0 ▸
864
Fencing
86.0 ▸
883
Landscape & Grounds
88.0 ▸
921
Punch List
92.4 ▸
944
Other Expenses-Con
94.0 ▸
Deal Cost Segments (7)
124
Buying
12.0 ▸
133
Financing
13.0 ▸
145
Holding Costs
14.0 ▸
935
Sale Preparation
90.0 ▸
950
Other Expenses-NonCon
— ▸
964
Selling
96.0 ▸
992
Sale
96.1 ▸
Part B — Work Order → Segment Connector

The 1:1 Mapping — Every Work Order Connects to Exactly One Segment

Hover any work order or segment to highlight its connection. Lines colored by phase: blue = P1, teal = P2, violet = P3. Administrative handoff WOs (no billing scope) shown in gray.

Phase 1 — Structure P1W01aSite ManagementP1W01a: Site Management P1W01bTree RemovalP1W01b: Tree Removal P1W02Utility Modification / Sewe…P1W02: Utility Modification / Sewer Systems P1W03DemolitionP1W03: Demolition P1W04Site WorkP1W04: Site Work P1W05FoundationP1W05: Foundation P1W06FramingP1W06: Framing P1W07RoofingP1W07: Roofing P1W08Windows & Exterior DoorsP1W08: Windows & Exterior Doors P1W09Interior StairsP1W09: Interior Stairs P1W10Siding & ShuttersP1W10: Siding & Shutters P1W11Gutters & LeadersP1W11: Gutters & Leaders P1W12End of Phase 1 HandoffP1W12: End of Phase 1 Handoff Phase 2 — Systems P2W01Phase 2 Pre-Takeover Walkth…P2W01: Phase 2 Pre-Takeover Walkthrough P2W02PlumbingP2W02: Plumbing P2W03HVACP2W03: HVAC P2W04ElectricalP2W04: Electrical P2W05Security & TechnologyP2W05: Security & Technology P2W06FireplacesP2W06: Fireplaces P2W07Insulation & SoundproofingP2W07: Insulation & Soundproofing P2W08DrywallP2W08: Drywall P2W09Exterior CarpentryP2W09: Exterior Carpentry P2W09bExterior MasonryP2W09b: Exterior Masonry P2W10Landscape & GroundsP2W10: Landscape & Grounds P2W11Yard FencingP2W11: Yard Fencing P2W12DrivewayP2W12: Driveway P2W13End of Phase 2 HandoffP2W13: End of Phase 2 Handoff Phase 3 — Finishes P3W01Phase 3 Pre-Takeover Walkth…P3W01: Phase 3 Pre-Takeover Walkthrough P3W02Tile InstallationP3W02: Tile Installation P3W03Flooring (Non-Tile)P3W03: Flooring (Non-Tile) P3W04CabinetryP3W04: Cabinetry P3W05Interior DoorsP3W05: Interior Doors P3W06Closet CarpentryP3W06: Closet Carpentry P3W07Basic TrimP3W07: Basic Trim P3W07aSpecialty Trim — MudroomP3W07a: Specialty Trim — Mudroom P3W07bSpecialty Trim — Coffered C…P3W07b: Specialty Trim — Coffered Ceilings P3W07cSpecialty Trim — Specialty …P3W07c: Specialty Trim — Specialty Walls P3W07dSpecialty Trim — Fireplace …P3W07d: Specialty Trim — Fireplace Specialty P3W07eSpecialty Trim — Specialty …P3W07e: Specialty Trim — Specialty Beams P3W07fSpecialty Trim — WainscotingP3W07f: Specialty Trim — Wainscoting P3W07gSpecialty Trim — Bookshelf …P3W07g: Specialty Trim — Bookshelf Built Ins P3W07hSpecialty Trim — Bench Buil…P3W07h: Specialty Trim — Bench Built Ins P3W07iSpecialty Trim — Specialty …P3W07i: Specialty Trim — Specialty Ceilings P3W07jSpecialty Trim — ShiplapP3W07j: Specialty Trim — Shiplap P3W08Painting & WallpaperP3W08: Painting & Wallpaper P3W09Countertops & StoneP3W09: Countertops & Stone P3W10Stain FinishingP3W10: Stain Finishing P3W11BacksplashP3W11: Backsplash P3W12Interior AccessoriesP3W12: Interior Accessories P3W13Door & Cabinet Knobs / Hard…P3W13: Door & Cabinet Knobs / Hardware P3W14MEP FinishesP3W14: MEP Finishes P3W15Shower Glass & Mirrors (Fra…P3W15: Shower Glass & Mirrors (Frameless) P3W16AppliancesP3W16: Appliances P3W17Final Punch ListP3W17: Final Punch List 18Site ManagementSegment 18: Site Management — 1 work order 88Landscape & GroundsSegment 88: Landscape & Grounds — 2 work orders 20Site SystemsSegment 20: Site Systems — 1 work order 32DemolitionSegment 32: Demolition — 1 work order 44Site WorkSegment 44: Site Work — 1 work order 42FoundationSegment 42: Foundation — 1 work order 52FramingSegment 52: Framing — 1 work order 53RoofingSegment 53: Roofing — 2 work orders 54Windows & Exterior DoorsSegment 54: Windows & Exterior Doors — 1 work order 56Interior StairsSegment 56: Interior Stairs — 1 work order 58Siding & ShuttersSegment 58: Siding & Shutters — 1 work order 63PlumbingSegment 63: Plumbing — 1 work order 62HVACSegment 62: HVAC — 1 work order 64ElectricalSegment 64: Electrical — 1 work order 65Security & TechnologySegment 65: Security & Technology — 1 work order 66FireplacesSegment 66: Fireplaces — 1 work order 67Insulation & Soundproof…Segment 67: Insulation & Soundproofing — 1 work order 69DrywallSegment 69: Drywall — 1 work order 82Exterior CarpentrySegment 82: Exterior Carpentry — 1 work order 84Exterior MasonrySegment 84: Exterior Masonry — 2 work orders 86FencingSegment 86: Fencing — 1 work order 71TileSegment 71: Tile — 2 work orders 72FlooringSegment 72: Flooring — 1 work order 73Cabinetry & CountertopsSegment 73: Cabinetry & Countertops — 2 work orders 74Interior CarpentrySegment 74: Interior Carpentry — 14 work orders 75Painting, Wallpaper & S…Segment 75: Painting, Wallpaper & Stain — 2 work orders 76AccessoriesSegment 76: Accessories — 2 work orders 77AppliancesSegment 77: Appliances — 1 work order 92Punch ListSegment 92: Punch List — 1 work order 16Project PrepSegment 16: Project Prep — 0 work orders 85Exterior PaintingSegment 85: Exterior Painting — 0 work orders 94Other Expenses-ConSegment 94: Other Expenses-Con — 0 work orders 12BuyingSegment 12: Buying — 0 work orders 13FinancingSegment 13: Financing — 0 work orders 14Holding CostsSegment 14: Holding Costs — 0 work orders 93Sale PreparationSegment 93: Sale Preparation — 0 work orders 95Other Expenses-NonConSegment 95: Other Expenses-NonCon — 0 work orders 96SellingSegment 96: Selling — 0 work orders 99SaleSegment 99: Sale — 0 work orders
↑ Scroll to see all 54 work orders · hover to highlight connections · hover a WO card in Part C to cross-link
Part C — Work Orders by Phase

What Each Work Order Is Authorized to Bill Against

Three phase columns — each is a bordered frame. WOs with multiple cost codes appear as full cards; simple WOs (≤1 code) and administrative milestones are compacted at the bottom of each phase. The segment tag (e.g. 52) shows which budget bucket this WO feeds. Hover any card to cross-highlight in the connector above.

Phase 1 — Structure13 WOs
P1W01a18
Site Management
18.0Site Management
18.1Dumpsters Ongoing
18.2Porta Potty Rental
18.6Temp Electric
18.7Silt Fence
18.8Project Fencing
18.9Site Supervision
P1W01b88
Tree Removal
88.7Tree Removal and Site Clean Up / Demo
88.8Landscape Improvements
P1W0220
Utility Modification / Sewer Systems
20.0Site Systems
22.0Utility Relocation
24.0Storage Tank Systems
24.4Storage Tank Repair
24.7Storage Tank Removal
24.8Storage Tank Installation
26.0Sewer and Septic Systems
26.4Sewer Line Repair
26.7Septic Installation
28.0Water and Well Systems
28.4Water Line Repair
28.7Well Repairs/Remediation
28.8New Well Install
28.9Pre-Sale Well Testing
29.0Other Site Systems and Amenities
29.1Other Site Systems and Amenities Materials
29.4Other Site Systems and Amenities Labor
P1W0332
Demolition
32.0Demolition Work
32.2Demo Materials/Tools/Rentals
32.3Dumpsters For Demo Only Not Ongoing
32.4Demolition Labor
32.7Demolition Flat Price
P1W0444
Site Work
40.0Foundation and Site Work
44.0Site Work
44.1Excavation/Backfill/Grading Materials
44.2Drainage Materials
44.3Retaining Wall Materials
44.4Excavation/Backfill/Grading Labor
44.5Drainage Labor
44.6Retaining Wall Labor
44.7Dirt Removal
44.8Drywell Labor
44.9Site Work Flat Price
P1W0542
Foundation
42.0Foundation
42.1Foundation Materials
42.4Foundation Labor (Mason)
P1W0652
Framing
50.0Framing and Shell
52.0Framing
52.1Standard Framing Materials
52.4Framing Labor
52.5Framing Labor Flat Price
P1W0753
Roofing
53.0Roofing
53.1Roofing Materials
53.4Roofing Labor
53.7Roofing Flat Price
P1W0854
Windows & Exterior Doors
54.0Windows and Exterior Doors
54.2Window Materials
54.3Exterior Door Materials
54.7Garage Doors
P1W0956
Interior Stairs
56.0Interior Stairs
56.1Interior Stair Materials
56.4Interior Stair Labor
P1W1058
Siding & Shutters
58.0Siding and Shutters
58.1House Wrap Materials
58.2Siding Materials
58.3Shutter Materials
58.4House Wrap Labor
58.5Siding Labor
58.6Shutter Labor
58.7House Wrap Flat Price
58.8Siding Flat Price
Simple / Admin
P1W1153
Gutters & Leaders
53.8Gutters/Leaders
P1W12
End of Phase 1 Handoff
Administrative milestone
Phase 2 — Systems14 WOs
P2W0263
Plumbing
63.0Plumbing
63.1Plumbing Rough Materials
63.2Plumbing Fixtures
63.4Plumbing Labor
63.7Plumbing Rough Flat Price
P2W0362
HVAC
62.0HVAC
62.1HVAC Materials
62.2Premium Thermostats
62.4HVAC Labor
62.7HVAC Flat Price
62.8HVAC Repair/Service
62.9HVAC Manuals
P2W0464
Electrical
64.0Electrical
64.1Electrical Materials Rough
64.2Electrical Fixtures
64.3Low Voltage Materials
64.4Electrical Labor
64.6Low Voltage Labor
64.7Electrical Flat Price
64.8Low Voltage Flat Price
P2W0666
Fireplaces
66.0Fireplaces
66.7Fireplace Flat Price
P2W0767
Insulation & Soundproofing
67.0Insulation
67.1Insulation/Fire Stop Materials
67.4Insulation/Fire Stop Labor
67.7Insulation/Fire Stop Flat Price
68.0Sound Proofing
68.1Sound Proofing Materials
68.4Sound Proofing Labor
68.7Sound Proofing Flat Price
P2W0869
Drywall
69.0Drywall
69.1Drywall/Spackle Materials
69.4Drywall/Spackle Labor
69.7Drywall/Spackle Flat Price
P2W0982
Exterior Carpentry
82.0Exterior Carpentry
82.1Deck/Porch Materials (carpentry)
82.2Exterior Railing Material
82.3Exterior Accessories
82.4Other Exterior Carpentry Labor
82.5Deck/Porch Labor (carpentry)
82.6Exterior Railing Labor
82.7Exterior Accessories Labor
P2W1088
Landscape & Grounds
88.0Landscape and Grounds
88.7Tree Removal and Site Clean Up / Demo
88.8Landscape Improvements
P2W1186
Yard Fencing
86.0Fencing
86.1Fencing Materials
86.4Fencing Labor
86.7Fencing Flat Fee
Simple / Admin
P2W01
Phase 2 Pre-Takeover Walkthrough
Administrative milestone
P2W0565
Security & Technology
65.0Security and Technology
P2W09b84
Exterior Masonry
84.8Patios, Walkways and Masonry Stairs (Flat Price)
P2W1284
Driveway
84.7Driveways (Flat Price)
P2W13
End of Phase 2 Handoff
Administrative milestone
Phase 3 — Finishes27 WOs
P3W0271
Tile Installation
71.0Tile Installation
71.1Tile Materials
71.4Tile Labor
P3W0372
Flooring (Non-Tile)
72.0Flooring Non-Tile
72.2Hardwood Floor Materials
72.3Vinyl Flooring Materials
72.5Hardwood Floor Labor
72.6Vinyl Flooring Labor
72.7Carpeting
P3W0473
Cabinetry
73.0Cabinetry
73.1Cabinet Materials
73.2Countertops
73.4Cabinet Labor
P3W0674
Closet Carpentry
74.2Closet Materials
74.5Interior Door Labor
74.6Closet Labor
P3W0774
Basic Trim
74.3Basic Trim Materials
74.7Basic Trim Labor
P3W07a74
Specialty Trim — Mudroom
74.4aMudroom - Materials
74.8aMudroom - Labor
P3W07b74
Specialty Trim — Coffered Ceilings
74.4bCoffered Ceilings - Materials
74.8bCoffered Ceilings - Labor
P3W07c74
Specialty Trim — Specialty Walls
74.4cSpecialty Walls - Materials
74.8cSpecialty Walls - Labor
P3W07d74
Specialty Trim — Fireplace Specialty
74.4dFireplace Specialty - Materials
74.8dFireplace Specialty - Labor
P3W07e74
Specialty Trim — Specialty Beams
74.4eSpecialty Beams - Materials
74.8eSpecialty Beams - Labor
P3W07f74
Specialty Trim — Wainscoting
74.4fWainscoting - Materials
74.8fWainscoting - Labor
P3W07g74
Specialty Trim — Bookshelf Built Ins
74.4gBookshelf Built Ins - Materials
74.8gBookshelf Built Ins - Labor
P3W07h74
Specialty Trim — Bench Built Ins
74.4hBench Built Ins - Materials
74.8hBench Built Ins - Labor
P3W07i74
Specialty Trim — Specialty Ceilings
74.4iSpecialty Ceilings - Materials
74.8iSpecialty Ceilings - Labor
P3W07j74
Specialty Trim — Shiplap
74.4jShiplap - Materials
74.8jShiplap - Labor
P3W0875
Painting & Wallpaper
75.0Painting and Wallpaper
75.1Paint Materials
75.2Wallpaper Materials
75.4Paint Labor
75.5Wallpaper Labor
P3W0973
Countertops & Stone
73.0Cabinetry
73.4Cabinet Labor
P3W1171
Backsplash
71.1Tile Materials
71.4Tile Labor
P3W1276
Interior Accessories
76.0Accessories
76.1Bathroom Materials Accessories / Small Mirrors
76.4Accessories Installation Labor
76.7Frameless Glass Enclosures and Mirrors
P3W1576
Shower Glass & Mirrors (Frameless)
76.1Bathroom Materials Accessories / Small Mirrors
76.7Frameless Glass Enclosures and Mirrors
P3W1677
Appliances
77.0Appliances
77.1Appliance Materials
77.4Appliance Installation Labor
Simple / Admin
P3W01
Phase 3 Pre-Takeover Walkthrough
Administrative milestone
P3W0574
Interior Doors
74.1Interior Door Materials
P3W1075
Stain Finishing
75.8Wallpaper Flat Price
P3W1374
Door & Cabinet Knobs / Hardware
74.1Interior Door Materials
P3W14
MEP Finishes
Administrative milestone
P3W1792
Final Punch List
92.4Punch List and Sale Prep Labor