Activity Log
Mon
Buyer's Final Walkthrough at 10am
Wed
Closing
QB recorded · $16.83M
— seg UNKNOWN: $13.87M, seg 99: $2.67M · PSE&G, NJ American Water — transaction dates may not match exact work timing
Mon
Finish Buyer's Punchlist
Tue
Finish Buyer's Punchlist
Wed
Closing
QB recorded · $20K
— seg 63: $9K, seg 52: $5K · NJ American Water, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Tony Driveway / Alberto Finish Landscaping
Tue
Buyer's Final Walkthrough
Wed
Finish All Punch List Items
Thu
CLOSING
QB recorded · $4K
— seg 84: $3K, seg 88: $1K · Buildesign Home Improvement, LLC, Garden State Construction (Asphalt) — transaction dates may not match exact work timing
Mon
De-Staging
Tue
Finish Buyer's Punchlist / Driveway
Wed
Nilson Flooring / Leo Complete Everything
Thu
Finish Buyer's Punchlist / Driveway
Fri
Finish Buyer's Punchlist / Driveway
QB recorded · $12K
— seg 93: $7K, seg 52: $4K · Zari Custom Homes Corporation, Elizabethtown Gas — transaction dates may not match exact work timing
Mon
Finish Buyer's Punchlist / Driveway
Tue
Finish Buyer's Punchlist / Driveway
Wed
Finish Buyer's Punchlist / Driveway
Thu
Finish Buyer's Punchlist / Driveway
Fri
Finish Buyer's Punchlist / Driveway
QB recorded · $668
— seg 13: $625, seg 14: $43 · Elizabethtown Gas, Yechezkel Litzman — transaction dates may not match exact work timing
Mon
Smoke Cert Inspection 9:30am-1:30pm
Tue
De-Stage
Wed
Nilson Fix Flooring / Paint Touch Ups as needed
Thu
Nilson Fix Flooring / Paint Touch Ups as needed
Fri
Nilson Fix Flooring / Paint Touch Ups as needed
QB recorded · $16K
— seg 75: $7K, seg 62: $6K · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Finalize Buyer's Inspection Plan
Tue
Buyer's Inspection
Wed
Rosario Onsite to Fix HVAC Items
Thu
Leo Onsite to Finish Up
Fri
Fricker Onsite 11am-1pm
QB recorded · $744
— seg 92: $660, seg 14: $84 · NJ American Water, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Review Buyer's Inspection
Tue
Buyer's Inspection / Bocked Sewer Line
QB recorded · $4K
— seg 53: $3K, seg 14: $748 · Elizabethtown Gas, PSE&G — transaction dates may not match exact work timing
Mon
Touch ups as needed
Tue
Touch ups as needed
Wed
Touch ups as needed
Thu
Touch ups as needed
Fri
Touch ups as needed
QB recorded · $693
— seg 92: $528, seg 76: $165 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Final Building, Mechanical and Electric Inspections 7:30am-2pm
Tue
Buyer's Inspection 11:30am
Wed
Touch ups as needed
Thu
Touch ups as needed
Fri
Touch ups as needed
QB recorded · $18K
— seg 13: $8K, seg 64: $4K · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Prep for Final Inspections / Gutter Install / Alberto Re-Hay
Tue
Final Inspections 7:30am-2pm
Wed
Finish Paver Install
Thu
Touch ups as needed
Fri
Touch ups as needed
QB recorded · $11K
— seg 63: $8K, seg 16: $3K · NJ American Water, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Touch ups as needed
Tue
Gutter Install / HVAC Finish Up
Wed
Gutter Install
Thu
Touch ups as needed
Fri
Touch ups as needed
QB recorded · $23K
— seg 84: $6K, seg 54: $4K · Elizabethtown Gas, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Video at 12pm
Tue
Photos at 1:30pm
Wed
Driveway Pour
Thu
Broker's Open 11-2pm
Fri
Garage Door Finish
QB recorded · $41K
— seg 58: $17K, seg 77: $6K · PSE&G, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Porch Work / Prep Nailers for Decorative Pine
Tue
Porch Work / Prep Nailers for Decorative Pine
Wed
Porch Work / Prep Nailers for Decorative Pine
Thu
New Year's Day
Fri
Replacement Doors arrive at BRL / Pick up Cabinets
QB recorded · $109K
— seg 13: $43K, seg 18: $20K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Mon
Deliver Cabinets to Woodream
Tue
Front Trex and Ceiling Pine Arrives / Prep Nailers for Decorative Pine
Wed
Porch Work / Prep Nailers for Decorative Pine
Thu
Christmas
Fri
Porch Work / Prep Nailers for Decorative Pine
QB recorded · $44K
— seg 58: $24K, seg 73: $13K · Buildesign Home Improvement, LLC, NJ American Water — transaction dates may not match exact work timing
Mon
Mudroom Built-ins / Paint / Backsplash
Tue
Mudroom Built-ins / Paint / Backsplash
Wed
Mudroom Built-ins / Paint / Backsplash
Thu
Decking Install / Paint / Backsplash
Fri
Decking Install / Paint / Backsplash
QB recorded · $15K
— seg 72: $8K, seg 82: $3K · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Mon
Wainscotting + Mudroom Cubby Install / Backsplash / Paint
Tue
Wainscotting + Mudroom Cubby Install / Backsplash / Paint
Wed
Wainscotting + Mudroom Cubby Install / Backsplash / Paint
Thu
Backsplash / Paint
Fri
Backsplash / Paint
QB recorded · $8K
— seg 74: $4K, seg 18: $2K · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Mon
Finish Floors
Tue
Deliver Cabinets to Woodream?
Wed
Floors Done
Thu
Protect Floors and Install Shoe
Fri
Protect Floors and Install Shoe
QB recorded · $23K
— seg 72: $16K, seg 73: $4K · Buildesign Home Improvement, LLC, PSE&G — transaction dates may not match exact work timing
Mon
Finish Carpentry / Countertop Template / Sinks Arrive
Tue
Finish Carpentry / Finish Floors
Wed
Deliver Cabinets to Woodream / Finish Floors
Thu
Thanksgiving Day
Fri
Finish Floors
QB recorded · $26K
— seg 13: $21K, seg 73: $2K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Mon
Trim + Closets
Tue
Cabinets Arrive (Knockdown)
Wed
Cabinet Assembly + Install
Thu
Cabinet Assembly + Install
Fri
Cabinet Install / Template
QB recorded · $19K
— seg 73: $11K, seg 74: $4K · Buildesign Home Improvement, LLC, NJ American Water — transaction dates may not match exact work timing
Mon
Trim + Closets
Tue
Trim + Closets
Wed
Trim + Closets
Thu
Trim + Closets
Fri
Trim + Closets
QB recorded · $17K
— seg 74: $8K, seg 73: $5K · Buildesign Home Improvement, LLC, Staples — transaction dates may not match exact work timing
Mon
Ceiling Herringbone Install
Tue
Post and Railing Install
Wed
Post and Railing Install
Thu
Trim + Closets
Fri
Trim + Closets
QB recorded · $13K
— seg 74: $7K, seg 18: $2K · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Finish Floor Install
Tue
Finish Floor Install
Wed
Trim + Closets
Thu
Trim + Closets
Fri
Trim + Closets
QB recorded · $40K
— seg 13: $21K, seg 74: $7K · Buildesign Home Improvement, LLC, Township of Scotch Plains — transaction dates may not match exact work timing
Mon
Wood Floor / Vinyl Install
Tue
Interior Doors & Trim Arrive
Wed
Door Install
Thu
Door Install
Fri
Trim Install
QB recorded · $29K
— seg 74: $20K, seg 88: $3K · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Tile / Vanity Install
Tue
Tile / Vanity Install
Wed
Wood and Vinyl Floor Install
Thu
Wood Floor Install
Fri
Wood Floor Install
QB recorded · $10K
— seg 71: $5K, seg 62: $3K · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Mon
Pending Gas / Tile Install / Flooring Delivery
Tue
Pending Gas / Tile Install / Vinyl Floor Install
Wed
Pending Gas / Tile Install / Vinyl Floor Install
Thu
Pending Gas / Tile Install / Vinyl Floor Install
Fri
Pending Gas / Vanity Install / Vinyl Floor Install
QB recorded · $21K
— seg 74: $13K, seg 71: $5K · J & M Contractors LLC, Jaeger Lumber — transaction dates may not match exact work timing
Mon
Pending Gas / Tile Install
Tue
Pending Gas / Tile Install
Wed
Pending Gas / Tile Install
Thu
Pending Gas / Tile Install
Fri
Pending Gas / Tile Install
QB recorded · $28K
— seg 13: $21K, seg 71: $5K · Ashpa Management, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Mon
Pending PSEG / Tile Install
Tue
Pending PSEG / Tile Install
Wed
Vanities Delivery / PSEG Hook up
Thu
Pending PSEG / Tile Install
Fri
Pending PSEG / Tile + Vanity Install
QB recorded · $7K
— seg 73: $4K, seg 71: $3K · Staples, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Mon
Pending PSEG Hook up
Tue
Pending PSEG Hook up / Tile
Wed
Pending PSEG Hook up / Tile
Thu
Pending PSEG Hook up / Tile
Fri
Pending PSEG Hook up / Tile
QB recorded · $2K
— seg 71: $2K, seg 14: $24 · NJ American Water, J & M Contractors LLC — transaction dates may not match exact work timing
Mon
Pending PSEG Hook up
Tue
Water Company Onsite 1:30-4:30pm
Wed
Pending PSEG Hook up
Thu
Pending PSEG Hook up
Fri
Pending PSEG Hook up
QB recorded · $10K
— seg 71: $7K, seg 64: $4K · Standard Tile, Jose Moreno (Electrician) — transaction dates may not match exact work timing
Mon
HVAC Unit Install
Tue
HVAC Unit Install
Wed
Pending PSEG Hook up
Thu
Pending PSEG Hook up
Fri
Pending PSEG Hook up
QB recorded · $4K
— seg 56: $2K, seg 18: $1K · Township of Scotch Plains, PSE&G — transaction dates may not match exact work timing
Mon
Pending HVAC Units
Tue
Pending HVAC Units
Wed
Pending HVAC Units
Thu
Pending HVAC Units
Fri
Pending HVAC Units
QB recorded · $56K
— seg 13: $21K, seg 69: $15K · Buildesign Home Improvement, LLC, Yover Tenezaca (Plumber) — transaction dates may not match exact work timing
Mon
Electric Service Inspection 9-1pm
Tue
Pending HVAC Units
Wed
Pending HVAC Units
Thu
Pending HVAC Units
Fri
Pending HVAC Units
QB recorded · $718
— seg 82: $372, seg 18: $322 · Buildesign Home Improvement, LLC, NJ American Water — transaction dates may not match exact work timing
Mon
Spackle Begins
Tue
Electric Service Inspection 9-1pm
Wed
Spackle
Thu
Wood Delivery
Fri
Spackle
QB recorded · $14K
— seg 62: $12K, seg 18: $1K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Mon
Sheetrock Delivery
Tue
Sheetrock Install
Wed
Sheetrock Install
Thu
Sheetrock Install
Fri
Sheetrock Install
QB recorded · $14K
— seg 69: $7K, seg 67: $6K · Buildesign Home Improvement, LLC, PSE&G — transaction dates may not match exact work timing
Mon
Framing and Ductwork Inspection 7:30am-2pm
Tue
Insulation Install
Wed
Insulation Install
Thu
Insulation Inspection 7:30am-2pm
Fri
Sheetrock Delivery
QB recorded · $246K
— seg UNKNOWN: $208K, seg 13: $19K · Buildesign Home Improvement, LLC, Township of Scotch Plains — transaction dates may not match exact work timing
Mon
Rough Plumbing Inspection 10-2pm
Tue
Finish Window Install
Wed
Fire Stop and Fire Block
Thu
Framing and Ductwork Inspection 7:30am-2pm
Fri
Insulation Install
QB recorded · $6K
— seg 52: $4K, seg 18: $2K · Buildesign Home Improvement, LLC, NJ American Water — transaction dates may not match exact work timing
Mon
Rough Plumbing Inspection 10-2pm / Hector + Andrew meet IT guy onsite 1-2pm
Tue
Ductwork / Framing Prep
Wed
Windows Arrive / Ductwork / Framing Prep
Thu
Window Install
Fri
Window Install
QB recorded · $22K
— seg 54: $13K, seg 52: $4K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Mon
Roughs
Tue
Roughs
Wed
Rough Inspections 7:30am-6:30pm
Thu
Fire Stop / Fire Block Install
Fri
Fire Stop / Fire Block Install
QB recorded · $22K
— seg UNKNOWN: $16K, seg 67: $4K · Buildesign Home Improvement, LLC, PSE&G — transaction dates may not match exact work timing
Mon
Roughs
Tue
Roughs
Wed
Roughs
Thu
Roughs
Fri
4th of July
QB recorded · $16K
— seg 63: $7K, seg 64: $4K · Buildesign Home Improvement, LLC, Chanan Feldman — transaction dates may not match exact work timing
Mon
Roughs / Finish Framing
Tue
Porch Footing Inspection 7:30-2pm
Wed
Roughs
Thu
Roughs
Fri
Roughs
QB recorded · $116K
— seg UNKNOWN: $100K, seg 13: $15K · Buildesign Home Improvement, LLC, NJ American Water — transaction dates may not match exact work timing
Mon
Roughs / Finish Framing
Tue
Roughs / Finish Framing
Wed
Roughs / Finish Framing
Thu
Roughs / Finish Framing
Fri
Roughs / Finish Framing
QB recorded · $16K
— seg 62: $9K, seg 66: $3K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Mon
Framing Stairs, Master Bedroom, and Basement
Tue
Framing Stairs, Master Bedroom, and Basement
Wed
Roughs
Thu
Roughs
Fri
Roughs
QB recorded · $17K
— seg 64: $8K, seg 52: $7K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Mon
Roof Install
Tue
Roof Install
Wed
Roughs
Thu
Roughs
Fri
Roughs
QB recorded · $12K
— seg 53: $5K, seg 52: $4K · Buildesign Home Improvement, LLC, Prestige Lighting — transaction dates may not match exact work timing
Mon
Cleaning (JJ)
Tue
Cleaning (JJ)
Wed
Staging
Thu
Staging
QB recorded · $23K
— seg 13: $18K, seg 32: $5K · AM & Sons Haulage LLC, Home Depot — transaction dates may not match exact work timing
Mon
Garage Door Install
Tue
Install Finishes
Wed
Glass Install
Thu
Glass Install
QB recorded · $203
— seg 18: $188, seg 32: $15 · Ashpa Management, American Royal Hardware — transaction dates may not match exact work timing
Mon
Appliance Install
Tue
Pick-up Hood @ Fabuwood
Wed
11am Site Walkthrough w/ Shlomo
Thu
Interior Cleaning
QB recorded · $5K
— seg 32: $5K, seg 16: $101 · Buildesign Home Improvement, LLC, Benchmark Excavating LLC — transaction dates may not match exact work timing
Mon
Porch Work / Siding
Tue
Segundo Finish Countertop Install
Wed
Confirm Glass Measurements / Siding
Thu
Appliances Arrive?