2087 Dogwood Completed

Scotch Plains · PM: Herson

Phase Timeline · QB spend = financial record (transaction dates may not match work timing)

P1
P1
Done ✓ · 32d behind
P2
P2
Done ✓ · 91d behind
P3
P3
Done ✓ · 46d behind
PM Delay Notes CO (soil paperwork, tempered windows) Smoke Cert CO (soil paperwork, tempered windows) Smoke Cert CO (soil paperwork, tempered windows) Smoke Cert CO (soil paperwork, tempered windows) Smoke Cert

Activity Log

Week of Apr 27, 2026 P3
Mon Buyer's Final Walkthrough at 10am
Wed Closing
QB recorded · $16.83M — seg UNKNOWN: $13.87M, seg 99: $2.67M · PSE&G, NJ American Water — transaction dates may not match exact work timing
Week of Apr 20, 2026 P3
Mon Finish Buyer's Punchlist
Tue Finish Buyer's Punchlist
Wed Closing
QB recorded · $20K — seg 63: $9K, seg 52: $5K · NJ American Water, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Apr 13, 2026 P3
Mon Tony Driveway / Alberto Finish Landscaping
Tue Buyer's Final Walkthrough
Wed Finish All Punch List Items
Thu CLOSING
QB recorded · $4K — seg 84: $3K, seg 88: $1K · Buildesign Home Improvement, LLC, Garden State Construction (Asphalt) — transaction dates may not match exact work timing
Week of Apr 6, 2026 P3
Mon De-Staging
Tue Finish Buyer's Punchlist / Driveway
Wed Nilson Flooring / Leo Complete Everything
Thu Finish Buyer's Punchlist / Driveway
Fri Finish Buyer's Punchlist / Driveway
QB recorded · $12K — seg 93: $7K, seg 52: $4K · Zari Custom Homes Corporation, Elizabethtown Gas — transaction dates may not match exact work timing
Week of Mar 30, 2026 P3
Mon Finish Buyer's Punchlist / Driveway
Tue Finish Buyer's Punchlist / Driveway
Wed Finish Buyer's Punchlist / Driveway
Thu Finish Buyer's Punchlist / Driveway
Fri Finish Buyer's Punchlist / Driveway
QB recorded · $668 — seg 13: $625, seg 14: $43 · Elizabethtown Gas, Yechezkel Litzman — transaction dates may not match exact work timing
Week of Mar 23, 2026 P3
Mon Smoke Cert Inspection 9:30am-1:30pm
Tue De-Stage
Wed Nilson Fix Flooring / Paint Touch Ups as needed
Thu Nilson Fix Flooring / Paint Touch Ups as needed
Fri Nilson Fix Flooring / Paint Touch Ups as needed
QB recorded · $16K — seg 75: $7K, seg 62: $6K · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 16, 2026 P3
Mon Finalize Buyer's Inspection Plan
Tue Buyer's Inspection
Wed Rosario Onsite to Fix HVAC Items
Thu Leo Onsite to Finish Up
Fri Fricker Onsite 11am-1pm
QB recorded · $744 — seg 92: $660, seg 14: $84 · NJ American Water, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Mar 9, 2026 P3
Mon Review Buyer's Inspection
Tue Buyer's Inspection / Bocked Sewer Line
QB recorded · $4K — seg 53: $3K, seg 14: $748 · Elizabethtown Gas, PSE&G — transaction dates may not match exact work timing
Week of Mar 2, 2026 P3
Mon Touch ups as needed
Tue Touch ups as needed
Wed Touch ups as needed
Thu Touch ups as needed
Fri Touch ups as needed
QB recorded · $693 — seg 92: $528, seg 76: $165 · Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Feb 23, 2026 P3
Mon Final Building, Mechanical and Electric Inspections 7:30am-2pm
Tue Buyer's Inspection 11:30am
Wed Touch ups as needed
Thu Touch ups as needed
Fri Touch ups as needed
QB recorded · $18K — seg 13: $8K, seg 64: $4K · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Feb 16, 2026 P3
Mon Prep for Final Inspections / Gutter Install / Alberto Re-Hay
Tue Final Inspections 7:30am-2pm
Wed Finish Paver Install
Thu Touch ups as needed
Fri Touch ups as needed
QB recorded · $11K — seg 63: $8K, seg 16: $3K · NJ American Water, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Feb 9, 2026 P3
Mon Touch ups as needed
Tue Gutter Install / HVAC Finish Up
Wed Gutter Install
Thu Touch ups as needed
Fri Touch ups as needed
QB recorded · $23K — seg 84: $6K, seg 54: $4K · Elizabethtown Gas, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Feb 2, 2026 P2
Mon Video at 12pm
Tue Photos at 1:30pm
Wed Driveway Pour
Thu Broker's Open 11-2pm
Fri Garage Door Finish
QB recorded · $41K — seg 58: $17K, seg 77: $6K · PSE&G, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Dec 29, 2025 P2
Mon Porch Work / Prep Nailers for Decorative Pine
Tue Porch Work / Prep Nailers for Decorative Pine
Wed Porch Work / Prep Nailers for Decorative Pine
Thu New Year's Day
Fri Replacement Doors arrive at BRL / Pick up Cabinets
QB recorded · $109K — seg 13: $43K, seg 18: $20K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Dec 22, 2025 P2
Mon Deliver Cabinets to Woodream
Tue Front Trex and Ceiling Pine Arrives / Prep Nailers for Decorative Pine
Wed Porch Work / Prep Nailers for Decorative Pine
Thu Christmas
Fri Porch Work / Prep Nailers for Decorative Pine
QB recorded · $44K — seg 58: $24K, seg 73: $13K · Buildesign Home Improvement, LLC, NJ American Water — transaction dates may not match exact work timing
Week of Dec 15, 2025 P2
Mon Mudroom Built-ins / Paint / Backsplash
Tue Mudroom Built-ins / Paint / Backsplash
Wed Mudroom Built-ins / Paint / Backsplash
Thu Decking Install / Paint / Backsplash
Fri Decking Install / Paint / Backsplash
QB recorded · $15K — seg 72: $8K, seg 82: $3K · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Dec 8, 2025 P2
Mon Wainscotting + Mudroom Cubby Install / Backsplash / Paint
Tue Wainscotting + Mudroom Cubby Install / Backsplash / Paint
Wed Wainscotting + Mudroom Cubby Install / Backsplash / Paint
Thu Backsplash / Paint
Fri Backsplash / Paint
QB recorded · $8K — seg 74: $4K, seg 18: $2K · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Dec 1, 2025 P2
Mon Finish Floors
Tue Deliver Cabinets to Woodream?
Wed Floors Done
Thu Protect Floors and Install Shoe
Fri Protect Floors and Install Shoe
QB recorded · $23K — seg 72: $16K, seg 73: $4K · Buildesign Home Improvement, LLC, PSE&G — transaction dates may not match exact work timing
Week of Nov 24, 2025 P2
Mon Finish Carpentry / Countertop Template / Sinks Arrive
Tue Finish Carpentry / Finish Floors
Wed Deliver Cabinets to Woodream / Finish Floors
Thu Thanksgiving Day
Fri Finish Floors
QB recorded · $26K — seg 13: $21K, seg 73: $2K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Nov 17, 2025 P2
Mon Trim + Closets
Tue Cabinets Arrive (Knockdown)
Wed Cabinet Assembly + Install
Thu Cabinet Assembly + Install
Fri Cabinet Install / Template
QB recorded · $19K — seg 73: $11K, seg 74: $4K · Buildesign Home Improvement, LLC, NJ American Water — transaction dates may not match exact work timing
Week of Nov 10, 2025 P2
Mon Trim + Closets
Tue Trim + Closets
Wed Trim + Closets
Thu Trim + Closets
Fri Trim + Closets
QB recorded · $17K — seg 74: $8K, seg 73: $5K · Buildesign Home Improvement, LLC, Staples — transaction dates may not match exact work timing
Week of Nov 3, 2025 P2
Mon Ceiling Herringbone Install
Tue Post and Railing Install
Wed Post and Railing Install
Thu Trim + Closets
Fri Trim + Closets
QB recorded · $13K — seg 74: $7K, seg 18: $2K · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Oct 27, 2025 P2
Mon Finish Floor Install
Tue Finish Floor Install
Wed Trim + Closets
Thu Trim + Closets
Fri Trim + Closets
QB recorded · $40K — seg 13: $21K, seg 74: $7K · Buildesign Home Improvement, LLC, Township of Scotch Plains — transaction dates may not match exact work timing
Week of Oct 20, 2025 P1
Mon Wood Floor / Vinyl Install
Tue Interior Doors & Trim Arrive
Wed Door Install
Thu Door Install
Fri Trim Install
QB recorded · $29K — seg 74: $20K, seg 88: $3K · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Oct 13, 2025 P1
Mon Tile / Vanity Install
Tue Tile / Vanity Install
Wed Wood and Vinyl Floor Install
Thu Wood Floor Install
Fri Wood Floor Install
QB recorded · $10K — seg 71: $5K, seg 62: $3K · J & M Contractors LLC, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Oct 6, 2025 P1
Mon Pending Gas / Tile Install / Flooring Delivery
Tue Pending Gas / Tile Install / Vinyl Floor Install
Wed Pending Gas / Tile Install / Vinyl Floor Install
Thu Pending Gas / Tile Install / Vinyl Floor Install
Fri Pending Gas / Vanity Install / Vinyl Floor Install
QB recorded · $21K — seg 74: $13K, seg 71: $5K · J & M Contractors LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Sep 29, 2025 P1
Mon Pending Gas / Tile Install
Tue Pending Gas / Tile Install
Wed Pending Gas / Tile Install
Thu Pending Gas / Tile Install
Fri Pending Gas / Tile Install
QB recorded · $28K — seg 13: $21K, seg 71: $5K · Ashpa Management, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Sep 22, 2025 P1
Mon Pending PSEG / Tile Install
Tue Pending PSEG / Tile Install
Wed Vanities Delivery / PSEG Hook up
Thu Pending PSEG / Tile Install
Fri Pending PSEG / Tile + Vanity Install
QB recorded · $7K — seg 73: $4K, seg 71: $3K · Staples, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Sep 15, 2025 P1
Mon Pending PSEG Hook up
Tue Pending PSEG Hook up / Tile
Wed Pending PSEG Hook up / Tile
Thu Pending PSEG Hook up / Tile
Fri Pending PSEG Hook up / Tile
QB recorded · $2K — seg 71: $2K, seg 14: $24 · NJ American Water, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Sep 8, 2025 P1
Mon Pending PSEG Hook up
Tue Water Company Onsite 1:30-4:30pm
Wed Pending PSEG Hook up
Thu Pending PSEG Hook up
Fri Pending PSEG Hook up
QB recorded · $10K — seg 71: $7K, seg 64: $4K · Standard Tile, Jose Moreno (Electrician) — transaction dates may not match exact work timing
Week of Sep 1, 2025 P1
Mon HVAC Unit Install
Tue HVAC Unit Install
Wed Pending PSEG Hook up
Thu Pending PSEG Hook up
Fri Pending PSEG Hook up
QB recorded · $4K — seg 56: $2K, seg 18: $1K · Township of Scotch Plains, PSE&G — transaction dates may not match exact work timing
Week of Aug 25, 2025 P1
Mon Pending HVAC Units
Tue Pending HVAC Units
Wed Pending HVAC Units
Thu Pending HVAC Units
Fri Pending HVAC Units
QB recorded · $56K — seg 13: $21K, seg 69: $15K · Buildesign Home Improvement, LLC, Yover Tenezaca (Plumber) — transaction dates may not match exact work timing
Week of Aug 18, 2025 P1
Mon Electric Service Inspection 9-1pm
Tue Pending HVAC Units
Wed Pending HVAC Units
Thu Pending HVAC Units
Fri Pending HVAC Units
QB recorded · $718 — seg 82: $372, seg 18: $322 · Buildesign Home Improvement, LLC, NJ American Water — transaction dates may not match exact work timing
Week of Aug 11, 2025 P1
Mon Spackle Begins
Tue Electric Service Inspection 9-1pm
Wed Spackle
Thu Wood Delivery
Fri Spackle
QB recorded · $14K — seg 62: $12K, seg 18: $1K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Aug 4, 2025 P1
Mon Sheetrock Delivery
Tue Sheetrock Install
Wed Sheetrock Install
Thu Sheetrock Install
Fri Sheetrock Install
QB recorded · $14K — seg 69: $7K, seg 67: $6K · Buildesign Home Improvement, LLC, PSE&G — transaction dates may not match exact work timing
Week of Jul 28, 2025 P1
Mon Framing and Ductwork Inspection 7:30am-2pm
Tue Insulation Install
Wed Insulation Install
Thu Insulation Inspection 7:30am-2pm
Fri Sheetrock Delivery
QB recorded · $246K — seg UNKNOWN: $208K, seg 13: $19K · Buildesign Home Improvement, LLC, Township of Scotch Plains — transaction dates may not match exact work timing
Week of Jul 21, 2025 P1
Mon Rough Plumbing Inspection 10-2pm
Tue Finish Window Install
Wed Fire Stop and Fire Block
Thu Framing and Ductwork Inspection 7:30am-2pm
Fri Insulation Install
QB recorded · $6K — seg 52: $4K, seg 18: $2K · Buildesign Home Improvement, LLC, NJ American Water — transaction dates may not match exact work timing
Week of Jul 14, 2025 P1
Mon Rough Plumbing Inspection 10-2pm / Hector + Andrew meet IT guy onsite 1-2pm
Tue Ductwork / Framing Prep
Wed Windows Arrive / Ductwork / Framing Prep
Thu Window Install
Fri Window Install
QB recorded · $22K — seg 54: $13K, seg 52: $4K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Jul 7, 2025 P1
Mon Roughs
Tue Roughs
Wed Rough Inspections 7:30am-6:30pm
Thu Fire Stop / Fire Block Install
Fri Fire Stop / Fire Block Install
QB recorded · $22K — seg UNKNOWN: $16K, seg 67: $4K · Buildesign Home Improvement, LLC, PSE&G — transaction dates may not match exact work timing
Week of Jun 30, 2025 P1
Mon Roughs
Tue Roughs
Wed Roughs
Thu Roughs
Fri 4th of July
QB recorded · $16K — seg 63: $7K, seg 64: $4K · Buildesign Home Improvement, LLC, Chanan Feldman — transaction dates may not match exact work timing
Week of Jun 23, 2025 P1
Mon Roughs / Finish Framing
Tue Porch Footing Inspection 7:30-2pm
Wed Roughs
Thu Roughs
Fri Roughs
QB recorded · $116K — seg UNKNOWN: $100K, seg 13: $15K · Buildesign Home Improvement, LLC, NJ American Water — transaction dates may not match exact work timing
Week of Jun 16, 2025 P1
Mon Roughs / Finish Framing
Tue Roughs / Finish Framing
Wed Roughs / Finish Framing
Thu Roughs / Finish Framing
Fri Roughs / Finish Framing
QB recorded · $16K — seg 62: $9K, seg 66: $3K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Jun 9, 2025 P1
Mon Framing Stairs, Master Bedroom, and Basement
Tue Framing Stairs, Master Bedroom, and Basement
Wed Roughs
Thu Roughs
Fri Roughs
QB recorded · $17K — seg 64: $8K, seg 52: $7K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Jun 2, 2025 P1
Mon Roof Install
Tue Roof Install
Wed Roughs
Thu Roughs
Fri Roughs
QB recorded · $12K — seg 53: $5K, seg 52: $4K · Buildesign Home Improvement, LLC, Prestige Lighting — transaction dates may not match exact work timing
Week of Jan 27, 2025
Mon Cleaning (JJ)
Tue Cleaning (JJ)
Wed Staging
Thu Staging
QB recorded · $23K — seg 13: $18K, seg 32: $5K · AM & Sons Haulage LLC, Home Depot — transaction dates may not match exact work timing
Week of Jan 20, 2025
Mon Garage Door Install
Tue Install Finishes
Wed Glass Install
Thu Glass Install
QB recorded · $203 — seg 18: $188, seg 32: $15 · Ashpa Management, American Royal Hardware — transaction dates may not match exact work timing
Week of Jan 13, 2025
Mon Appliance Install
Tue Pick-up Hood @ Fabuwood
Wed 11am Site Walkthrough w/ Shlomo
Thu Interior Cleaning
QB recorded · $5K — seg 32: $5K, seg 16: $101 · Buildesign Home Improvement, LLC, Benchmark Excavating LLC — transaction dates may not match exact work timing
Week of Jan 6, 2025
Mon Porch Work / Siding
Tue Segundo Finish Countertop Install
Wed Confirm Glass Measurements / Siding
Thu Appliances Arrive?