63 Montclair Completed

Montclair · PM: Herson

Phase Timeline · QB spend = financial record (transaction dates may not match work timing)

P1
P1
Done ✓ · 70d behind
P2
P2
Done ✓ · on schedule
P3
P3
Done ✓ · 24d behind
PM Delay Notes CO Smoke Cert Pocket Door Remove From Vacant Register - Reach out James Code Violation? Clear These Up CO Smoke Cert Code Violation? Clear These Up

Activity Log

Week of Dec 29, 2025 P3
Mon Punchlist
Tue In-House Photos 11:30am
Wed Punchlist
Thu New Year's Day
Fri Punchlist
QB recorded · $53K — seg 18: $24K, seg 13: $20K · Wallworks Painting & Wallpaper, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Dec 22, 2025 P3
Mon Punchlist
Tue Punchlist
Wed Punchlist
Thu Christmas
Fri Punchlist
QB recorded · $15K — seg 75: $4K, seg 93: $4K · Buildesign Home Improvement, LLC, Home Depot — transaction dates may not match exact work timing
Week of Dec 15, 2025 P3
Mon Staging / Water Meter Install 9am
Tue Photos at 10am
Wed Touch Ups
Thu Broker Open 10:30am-12:30pm
Fri Touch Ups
QB recorded · $34K — seg 58: $14K, seg 75: $6K · Buildesign Home Improvement, LLC, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Dec 8, 2025 P2
Mon Post, Spindle, Railing Install
Tue Appliance Delivery
Wed Appliance Install
Thu Fence Install / Driveway Pour
Fri Fence Install
QB recorded · $249K — seg UNKNOWN: $200K, seg 72: $15K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Dec 1, 2025 P2
Mon Finish Siding / Paver Install / Ext. Porch Work
Tue Deliver Cabinets to Woodream?
Wed Paver Install / Ext. Porch Work
Thu Cabinet Hardware + Finishes
Fri Ernie onsite to finish fireplace / Gutter Install
QB recorded · $52K — seg 77: $12K, seg 75: $9K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Nov 24, 2025 P2
Mon Paver Install / Backsplash + Porch Work
Tue Paver Install / Backsplash + Porch Work
Wed Deliver Cabinets to Woodream
Thu Thanksgiving Day
Fri Porch Work + Finishes Install
QB recorded · $27K — seg 13: $16K, seg 74: $2K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Nov 17, 2025 P2
Mon Soffit Arrives / Decking + Shoe Install
Tue Decking + Shoe Install / Paint Prep
Wed Paint Prep / Decking
Thu Paint Prep / Porch Ceiling Install
Fri Paint Prep / Porch Ceiling Install
QB recorded · $37K — seg 64: $8K, seg 63: $7K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Nov 10, 2025 P2
Mon Finish Floors / Front Porch Framing
Tue Finish Floors / Front Porch Framing / Trex Decking Install
Wed Back Ordered Cabinets Arrive / Trex Decking Install
Thu Finish Cabinet Install / Cover Floors / Trex Decking Install
Fri Finish Cabinet Install / Cover Floors / Fireplace Exhaust Install
QB recorded · $7K — seg 52: $3K, seg 18: $1K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Nov 3, 2025 P2
Mon Finish Fixing Interior Stairs / Backordered Cabinets Arrive
Tue Countertop Templating / Trex Deck Arrives
Wed Finish Floors
Thu Finish Floors
Fri Finish Floors
QB recorded · $7K — seg 58: $2K, seg 73: $1K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Oct 27, 2025 P2
Mon Finish Cabinet Install
Tue Finish Cabinet Install
Wed Siding
Thu Siding
Fri Siding
QB recorded · $43K — seg 13: $16K, seg 14: $8K · Amazon, Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Oct 20, 2025 P2
Mon Kitchen, Wine Bar, Laundry Room Cabinets Arrive
Tue Cabinet Install / Decking Install
Wed Siding Arrives / Cabinet Install
Thu Siding Install / Countertop Template
Fri Siding Install / Countertop Template
QB recorded · $31K — seg 58: $19K, seg 74: $7K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Oct 13, 2025 P2
Mon Trim / Tile / Closets
Tue Trim / Tile / Closets
Wed Trim / Tile / Closets / Decking
Thu Decking
Fri Decking
QB recorded · $24K — seg 73: $14K, seg 74: $5K · Buildesign Home Improvement, LLC, Township of Montclair — transaction dates may not match exact work timing
Week of Oct 6, 2025 P2
Mon Back Deck Material Arrives
Tue Trim / Tile / Closets / Decking
Wed Trim / Tile / Closets / Decking
Thu Trim / Tile / Closets / Decking
Fri Trim / Tile / Closets / Decking
QB recorded · $15K — seg 74: $8K, seg 71: $2K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Sep 29, 2025 P2
Mon Tile Prep, Tile Install + Trim Install
Tue Finish Flooring + Bullnose Install
Wed Tile Prep, Tile Install + Trim Install
Thu Tile Prep, Tile Install + Trim Install
Fri Tile Prep, Tile Install + Trim Install
QB recorded · $25K — seg 13: $15K, seg 82: $3K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Sep 22, 2025 P1
Mon Interior Door and Trim Delivery
Tue Door + Trim + Tile Install
Wed Door + Trim + Tile Install
Thu Door + Trim + Tile Install
Fri Door + Trim + Tile Install
QB recorded · $32K — seg 74: $20K, seg 69: $6K · Advanced Flooring, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Sep 15, 2025 P1
Mon Framing Edits, Interior Stair Fix
Tue Framing Edits, Interior Stair Fix, Prep for Flooring Install
Wed Framing Edits, Interior Stair Fix, Prep for Flooring Install
Thu Floor Install
Fri Trim Install
QB recorded · $9K — seg 71: $5K, seg 66: $950 · Jaeger Lumber, Noble Builders & Fireplaces LLC — transaction dates may not match exact work timing
Week of Sep 8, 2025 P1
Mon Spackle / Furnace Install
Tue Spackle / Furnace Install
Wed Spackle / Turn on Furnaces / Floor Delivery
Thu Spackle
Fri Complete Spackle / Clean out for Floor Install
QB recorded · $8K — seg 69: $6K, seg 53: $1K · Jaeger Lumber, Ashpa Management — transaction dates may not match exact work timing
Week of Sep 1, 2025 P1
Mon Sheetrock Install
Tue Sheetrock Install
Wed Sheetrock Install
Thu Sheetrock Install
Fri Flooring Delivery? (need to turn on furnaces)
QB recorded · $4K — seg 64: $3K, seg 52: $800 · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Aug 25, 2025 P1
Mon Prep for Sheetrock Install / Front Door Install
Tue Sheetrock Delivery / Front Door Install
Wed Sheetrock Install
Thu Sheetrock Install
Fri Sheetrock Install
QB recorded · $72K — seg 13: $16K, seg 69: $11K · Buildesign Home Improvement, LLC, Blue Ridge Lumber — transaction dates may not match exact work timing
Week of Aug 18, 2025 P1
Mon Fire Stop / Fire Block
Tue Above Ceiling Ductwork and Framing Inspection 8am-1pm
Wed Insulation Install
Thu Insulation Install
Fri Insulation Inspection 8am-1pm
QB recorded · $16K — seg 14: $11K, seg 64: $3K · Jose Moreno (Electrician), Buildesign Home Improvement, LLC — transaction dates may not match exact work timing
Week of Aug 11, 2025 P1
Mon Plumbing / HVAC
Tue Plumbing / HVAC
Wed Plumbing / HVAC
Thu Fire Stop / Fire Block Plumbing / HVAC
Fri Rough Plumbing and Gas Pressure Test 8am-1pm
QB recorded · $12K — seg 88: $6K, seg 62: $5K · Buildesign Home Improvement, LLC, Eduar Raudales — transaction dates may not match exact work timing
Week of Aug 4, 2025 P1
Mon Roughs / Framing (In-house)
Tue Roughs / Framing (In-house)
Wed Roughs / Framing (In-house)
Thu Roughs / Framing (In-house)
Fri Rough Electric and Electric Trench Inspection 8am-1pm
QB recorded · $9K — seg 52: $6K, seg 64: $2K · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Jul 28, 2025 P1
Mon Electric / PVC / Framing (In-house)
Tue Tree Removal
Wed Roughs / Framing (In-house)
Thu Roughs / Framing (In-house)
Fri Roughs / Framing (In-house)
QB recorded · $29K — seg 13: $15K, seg 52: $6K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Jul 21, 2025 P1
Mon Window Install / Framing Material Arrives
Tue Window Install / Electric / PVC / Framing (In-house)
Wed Electric / PVC / Framing (In-house)
Thu Electric / PVC / Framing (In-house)
Fri Electric / PVC / Framing (In-house)
QB recorded · $14K — seg 52: $8K, seg 88: $6K · Buildesign Home Improvement, LLC, A-R General Contractor_Alberto Landscape & Snow Removal — transaction dates may not match exact work timing
Week of Jul 14, 2025 P1
Mon Electric
Tue Electric
Wed Electric / PVC Plumbing
Thu Windows Arrive
Fri Electric
QB recorded · $43K — seg 54: $31K, seg 63: $9K · Buildesign Home Improvement, LLC, Township of Montclair — transaction dates may not match exact work timing
Week of Jul 7, 2025 P1
Mon Fireplace Install / Small Framing Mods
Tue Plumbing Roughs Arrive / Fireplace Install / Small Framing Mods
Wed PVC Plumbing
Thu PVC Plumbing
Fri PVC Plumbing
QB recorded · $57K — seg UNKNOWN: $43K, seg 52: $6K · PSE&G, Bergen-Essex Contractors Inc — transaction dates may not match exact work timing
Week of Jun 30, 2025 P1
Mon Small Framing Mods
Tue Small Framing Mods
Wed Small Framing Mods / PVC Plumbing
Thu PVC Plumbing
Fri 4th of July
QB recorded · $38K — seg 52: $19K, seg 13: $15K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Jun 23, 2025
Mon Roof Install
Tue Back Deck Footing Inspection 8-1pm
Wed Window Delivery (afternoon)
Thu Window + Door Install
Fri Window + Door Install
QB recorded · $2K — seg 52: $2K, seg 14: $526 · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Jun 16, 2025
Mon Framing
Tue Framing
Wed Framing
Thu Roof Install
Fri Roof Install
QB recorded · $18K — seg 14: $13K, seg 44: $3K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Jun 9, 2025
Mon Framing
Tue Framing
Wed Framing
Thu Framing
Fri Framing
QB recorded · $8K — seg 52: $5K, seg 44: $1K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Jun 2, 2025
Mon PSLs Arrive
Tue Decking Install
Wed Backfill and Grading
Thu Backfill and Grading
Fri Tree Removal / Framing
QB recorded · $16K — seg 52: $15K, seg 18: $1K · Buildesign Home Improvement, LLC, Ashpa Management — transaction dates may not match exact work timing
Week of Apr 28, 2025
Mon Slab Materials Arrive
Tue Slab Prep
Wed Footing and Slab Inspections 8-1pm
Thu Concrete Truck 9am SRM / Dirt Trucking
Fri Foundation Install
QB recorded · $30K — seg 13: $15K, seg 42: $8K · Buildesign Home Improvement, LLC, Township of Montclair — transaction dates may not match exact work timing
Week of Apr 21, 2025
Mon Footing and Slab Work
Tue Slab Plumbing Inspection 8-1pm
Wed Footing / Slab Work (if able today in regard to 2087D)
Thu Footing / Slab Work
Fri Footing / Slab Work
QB recorded · $3K — seg 42: $2K, seg 20: $520 · Buildesign Home Improvement, LLC, J & M Contractors LLC — transaction dates may not match exact work timing
Week of Apr 14, 2025
Mon Slab "Underpinning" Work
Tue Concrete Truck 1pm (Footings)
Wed Slab "Underpinning" / Foundation Install
Thu Foundation Install
Fri Foundation Install
QB recorded · $4K — seg 42: $4K, seg 18: $285 · Buildesign Home Improvement, LLC, Township of Montclair — transaction dates may not match exact work timing
Week of Apr 7, 2025
Mon Clean for Footing Install Tomorrow
Tue Footing Install
Wed Footing Install
Thu Footing Install
Fri Footing Inspection 8-1pm
QB recorded · $7K — seg 32: $2K, seg 44: $2K · Buildesign Home Improvement, LLC, Jaeger Lumber — transaction dates may not match exact work timing
Week of Mar 31, 2025
Mon Excavation and Demo (weather permitting)
Tue Excavation and Demo / Dirt Truck (Jose)
Wed Excavation and Demo / Dirt Truck (Jose)
Thu Excavation
Fri Footing Prep
QB recorded · $17K — seg 13: $15K, seg 44: $2K · Jaeger Lumber, Yosef Hott — transaction dates may not match exact work timing
Week of Mar 24, 2025
Mon Charlie Begins Demo / Excavation
Tue Charlie Begins Demo / Excavation
Wed Excavation / Dump Truck to Haul Dirt
Thu Excavation / Dump Truck to Haul Dirt
Fri Footing Prep
QB recorded · $135 — seg 18: $135 · Ashpa Management — transaction dates may not match exact work timing
Week of Mar 17, 2025
Mon Meet Charlie Onsite and Finalize SOW
Tue Begin Demo and Excavation
Wed Demo and Excavation
Thu Demo and Excavation
Fri Demo and Excavation
QB recorded · $197 — seg 16: $197 · Staples — transaction dates may not match exact work timing
Week of Mar 10, 2025
Mon Dig for Footings
Tue Dig for Footings
Wed Dig for Footings
Thu Footing Prep
Fri Footing Prep
Week of Jan 13, 2025
Mon Smoke Cert Inspection 10am-12pm / Buyer Punchlist
Tue Buyer's Final Walkthrough
Wed Closing
QB recorded · $488 — seg 12: $488 · Simple Tank Services — transaction dates may not match exact work timing
Week of Jan 6, 2025
Mon Prep for Buyer's Inspection
Tue Buyer's Inspection 11am
Wed Final Building Inspection 8-1pm
Thu De-Stage?